Bid Status
Project | Job | Value | Status |
---|---|---|---|
North Yarra Main Relining Upper Section | Y10234 | $13M | Working |
Project Delivery Update
M76 Water Main Renewal ~ Q02707 |
- Still awaiting APN.
- Notifications for early works investigations (service location and proving) has been issued to stakeholders.
Essex Main Drain Renewal ~ Y10314 |
- Draft APN issued for review and comment.
- Day 1 readiness procedures and tasks have commenced.
Maribyrnong Main Sewer Augmentation ~ P31258 |
- Launch Shaft depth: 32.2m.
- Sheet Piling ground stabilization solution dismissed due to piling intrusion into tunnel, excessive cost and timing considerations for required piles.
- Geotech investigation complete (x3 boreholes).
- Dewatering commenced (introduced to x3 boreholes). Pursuing grout injection via specialist subcontractor to stabilise Brighton Group Layer.
- Estimated program delay approx. 2 months.
- Riverside:
- Churchill Drain crossing complete.
- Vegetation stripping and access track construction including Shared User Path subgrade continuing.
- Receival shaft excavation progressing depth: 4.8m.
- Bridge package RFA: Delfab.
- Piling RFQ issued, poor response, further work needed.
Yan Yean WTP Upgrade~ Q04385 |
- Continue mechanical and electrical fit-out.
- Final Energization Plan and Commissioning Plan submitted.
- Mechanical pre-commissioning commenced.
- Energization scheduled late May 23
Yan Yean Pump Station ~ Q05322 |
- Bulk earthworks completed.
- Structural concrete commenced.
Yan Yean Bald Hill Pipeline ~ Q05333 |
- Still waiting for final environmental approvals from Whittlesea Council, delays are associated with incorporating the pumpstation permit conditions into the pipeline planning permit. Melbourne Water forgot to request approval for vegetation clearing at pump station site.
- EOT being submitted for the approval of CHMP West delay to start of project
- Working with Winslow and subcontractors to re validate pricing/subcontracts.
- Audit completed some minor actions and administrative actions to close out
Hoppers Crossing Pump Station 66kV ~ F10428 |
- Detailed design for the 80% design package has been issued to Melbourne Water for review.
- Q03109 Power Reliability – early works of this scope is underway. Load study and HV Circuit Breaker specification has been issued to Melbourne Water. Meeting was held between Melbourne Water/SFP to discuss concept design. Melbourne Water have determined the options provided were not acceptable – a new location is to be reviewed by SFP.
- SFP attended site to inspect new nominated location. Location will be reviewed and further information will be requested in order to proceed.
- Early procurement of Siemens circuit breaker has been approved for the pending Power Reliability variation works. Currently in negotiations with Siemens.
WTP 25W Lagoon Pond 1 HV and LV Renewals ~ F10461 |
- Design
- LV Control Narrative – Updated document issued for Melbourne Water review.
- HV Control Narrative – Updated document issued for Melbourne Water review.
- LV Protection and Arc Flash Report – Updated document issued for Melbourne Water review.
- HV Protection Report – Updated document issued for Melbourne Water review.
- HV Arc Flash Report – Response to Melbourne Water comments sent.
- RMU Control Panel – IFC drawings being finalised.
- Procurement
- MLCs – All MLCs have been delivered.
- RMU – Delivered to Accenture for the control panel installation.
- All HV, LV and FO cables have been delivered.
- Construction
- Install FO cable from 48ZDA to NE corner of 25W Pond 1.
- Install ladder lids on aerator stands along South Rd.
- Roping of existing FO conduits along North Rd.
- Delivery and installation of 48ZAB and 48ZAA MLCs.
- Pre-commissioning and testing of 48ZDB and 48ZDA MLCs.
ETP HV-62A Switchboard & VH-LV Renewals ~ Y10307 (Q05103) |
- Completed removal of OSS T1 and T2 heat exchangers including associated pipe work.
- Completed cutover works of 6.6kV 33H feeder from 62H to new 62HA.
- Continued civil works for 33H cutover including cable pit modifications.
- Completed cable installation on second 54M feeder. 1 cable 350m.
- Started cutover works of 6.6kV 71M feeder from 62H to new 62HA.
ETP Waste Activated Sludge ~ Q05102 |
- DAF 8,11 & 12 Commissioning Report submitted to MW. Working through Melbourne Water comments
- DAF 1 beach plate modification complete
- DAF 7 fitout works complete. Additional scope to rectify DAF 7 flights planned to commence 01/05/23
ETP Recuperative Thickener ~ Q05772 |
- Second 14 day PoPT in progress.
Gardiners Creek Sewer Rehabilitation ~ Y10248 |
- Final agreement on payment of works to complete the project has been finalised.
Holden Reservoir M486 Inlet Pipeline SP1 & SP2~ Q03295 |
- Stage 1 certificate received 8 April, 2022.
- Awaiting Melbourne Water to provide data for Stage 2 and 3.