Bid Status

ProjectJobValueStatus
ETP Areas 15-26 UpgradesF10730$22.4MWon
WTP 55E Pond 1 MLC RenewalF10427$14.9MWon
WTP HV Power & Energy Resilience ECIQ03817$472KWon
ETP Power Management ChangesH11894$482KSubmitted
Quarry Hill TankF10365$18.8MLost
Mordialloc Main Sewer RehabY10341$12.4MSubmitted
Refurb of Werribee Hanger 1Y05707$23MSubmitted
ETP Digester UpgradesY10286$70MSubmitted
Thomson Dam Capacitor UpgradeY10364$3.5MWorking
Tarago Fluoride Plant UpgradeY10209$10MSubmitted
WTS Emergency Management PlanQ05622$250kWorking

Project Delivery Update

North Yarra Main Relining Upper Section ~ Y10234
  • All MH modifications pre-lining completed
  • All spiral lining completed
  • 50% MH reinstatement completed

M76 Water Main Renewal ~ Q02707
  • Pipelaying ongoing in High Street Rd to chainage 945m of 1160m.
  • Lawrence Street crossing completed
  • Completed approx 60m in Fleet St
  • Commenced St Alban St works in preparation for connection works

Essex Main Drain Renewal ~ Y10314
  • Garden St works completed including reinstatement
  • Early Works for Erica St change event completed
  • Rehabilitation Works at Dye Works Park ongoing

Maribyrnong Main Sewer Augmentation ~ P31258
  • Launch Shaft
    • 777m complete (89m for April).
    • High jacking forces in excess of 5000kN the first 400m has resulted in ovality issues and pipe damage at multiple locations. Pipe ovality is being managed through the installation of steel support sleeves.
    • Slurry Pump 2.2 failed and has been bypassed.
    • Temp works design and procurement for Adit construction ongoing
  • Riverside:
    • Direction Notice #1: Site has been demobilised.
    • Direction Notice #2: Updated Budget pricing incorporating Geotech information and Temp works shaft design in work ongoing.
Yan Yean WTP Upgrade~ Q04385
  • Completed temporary PLC cutover
  • PoPT commenced 9 April. On pause from 26 April to implement flushing
  • PoPT to recommence late May
Yan Yean Pump Station ~ Q05322
  • Commissioning on suction and discharge pipework in progress
  • Electrical installation works completed and energisation of RMU scheduled for 2 May
  • Site remediation in progress
  • Mechanical works completed
  • Landscaping and roadworks in progress
Yan Yean Bald Hill Pipeline ~ Q05333
  • Pipe install completed to base of Bald Hill
  • Pipe install at 89% complete
  • Shaft construction at Merri Creek underway:
    • Receival shaft down to invert
    • Launch Shaft down 11m
  • TBM equipment tunnelling team mobilising first week of May
Hoppers Crossing Pump Station 66kV ~ F10428
  • Design – Progressing to next milestone (IFC)
  • CE03 – Escalation Costs on Main Project delay due to Q03109. Approximately $536k. Submitted to Melbourne Water on 8 December.
WTP 25W Lagoon Pond 1 HV and LV Renewals ~ F10461
  • All kiosks commissioned and energised.
  • PC Stage 1 achieved 28 March.  
 WTP 55 East HV/LV (CE to 25W)
  • DGM activities in progress.
 WTP 66kV
  • Early works – design approved and in progress
Thompson Hydro Capacitor Bank – Y10364
  • APN received for early procurement.
ETP Waste Activated Sludge ~ Q05102
  • Report to be provided for TWAS pump performance
  • Final Proof of Performance to commence May
ETP Recuperative Thickener ~ Q05772
  • Closing out Stage 2 items.