Bid Status

ProjectJobValueStatus
ETP Areas 15-26 UpgradesF10730$22.4MSubmitted – Preferred Awaiting PN
ETP Power Management ChangesH11894$482KSubmitted – Delayed
WTP 55E Pond 1 MLC RenewalF10427$14.9MWon
WTP HV Power & Energy Resilience ECIQ03817$472KAwaiting PN
Refurb of Werribee Hanger 1Y05707$23MWorking
Quarry Hill TankF10365$9MWorking
Mordialloc Main Sewer RehabY10341$9MWorking
ETP Digester UpgradesY10286$70MWorking
Thomson Dam Capacitor UpgradeY10364$3.5MWorking
Tarago Fluoride Plant UpgradeY10209$10MWorking


Project Delivery Update

North Yarra Main Relining Upper Section ~ Y10234
  • Cleaning Section B (NYM119-112) started.
  • Lining of 5No sewer sections completed with spiral PVC in section A.
  • 4No lines 376m of 450mmØ sewer
  • 1No line 38m of 600mmØ sewer

Tarago Fluoride Plant Upgrade ECI ~ Y10209
  • ECI completed.
M76 Water Main Renewal ~ Q02707
  • Pipelaying ongoing in High Street Rd to chainage 292m of 1160m.

Essex Main Drain Renewal ~ Y10314
  • First culvert installed at Garden Street.

Maribyrnong Main Sewer Augmentation ~ P31258
  • Launch Shaft
    • 587m complete (approx. 73% – 7th Feb 2024). Currently tunnelling through basalt and this material is expected to continue for the remainder of the tunnel, rock strength remains within limits of the Geotech Baseline Report.
    • Temp works design and procurement for Adit construction underway.
  • Riverside:
    • Direction Notice #1 – Site has been demobilised.
    • Direction Notice #2: Siphon options assessment complete. Updated Budget pricing incorporating Geotech information and Temp works shaft design in work
    • HEC-RAS flood calibration draft report submitted.
    • Report to be updated and resubmitted.
Yan Yean WTP Upgrade~ Q04385
  • DHSS approval on FSA system obtained and FSA delivered to site
  • 24 hour operation of plant commenced
  • Proof of Performance Test scheduled to commence Feb 2024
Yan Yean Pump Station ~ Q05322
  • Mechanical installation continues in pump hall.
  • HV and LV switchboard installation complete.
  • Electrical fitout 80% completed.
  • Underground discharge installation continues.
Yan Yean Bald Hill Pipeline ~ Q05333
  • Productivities are improving , AMES due to finish Grants Rd by early Feb. 
  • Overall works are 69% complete.
  • Commissioning strategy agreed and commissioning plan submitted.
  • Delays to program due to change in tunnel contractor
Hoppers Crossing Pump Station 66kV ~ F10428
  • RMU offers have been received. Award is expected to be in January 2024.
  • Powercor has completed their review; agreement has been reached between Powercor & SFP on 13/12/2023. Allowance will be made in the MW protection panels for interface with future.
  • CE03 – Escalation Costs on Main Project delay due to Q03109. Approximately $536k. Submitted to Melbourne Water on 8 December.
WTP 25W Lagoon Pond 1 HV and LV Renewals ~ F10461
  • Civil
    • Service locating around 48XA02 kiosk slab.
    • Service locating at old MLC slabs around pond 1.
  • Electrical
    • 48XA01 kiosk commissioned.
ETP HV-62A Switchboard & VH-LV Renewals ~ Y10307 (Q05103)
  • Works Completed on site.
ETP Waste Activated Sludge ~ Q05102
  • Report to be provided  for TWAS pump performance
  • Final Proof of Performance to commence
ETP Recuperative Thickener ~ Q05772
  • Closing out Stage 2 items