Bid Status
Project | Job | Value | Status |
---|---|---|---|
Essex Street Main Drain Renewal | Y10314 | $4.9M | Submitted |
M76 Pipeline Renewal | Q02707 | $21.7M | Submitted |
Hoppers Crossing Power Reliability System Upgrade | Q03109 | $3M | Won |
Project Delivery Update

Holden Reservoir M486 Inlet Pipeline SP1 & SP2~ Q03295 |
- Stage 1 certificate received 8 April, 2022.
- Awaiting Melbourne Water to provide data for Stage 2 and 3.

Yan Yean WTP Upgrade~ Q04385 |
- Continue mechanical and electrical fit-out.
Yan Yean Pump Station ~ Q05322 |
- Commenced tree removal 30 January.
- Planning in progress for bulk earthworks commenced on site.
Yan Yean Bald Hill Pipeline ~ Q05333 |
- CHMP east completed planning permit conditions received and being responded to final planning permit should be received from Whittlesea late February.
- CHMP West resubmitted with likely approval late February.
- Delay still ongoing.
- TCC review completed some minor updates undertaken and submitted with an Audit booked in for February.

ETP HV-62A Switchboard & VH-LV Renewals ~ Y10307 (Q05103) |
- Achieved successful plant wide shutdown for switchboard cutover.
- Continued civil works for 62M transformers.
- Removed redundant equipment for OSS T1 Vault.
- Completed HV cable termination at 84EH.
- Continued new T2 pre commissioning.
- Completed punch list items in 62HA.

ETP Recuperative Thickener ~ Q05772 |
- Proof of Performance test commenced 31 January

ETP Waste Activated Sludge ~ Q05102 |
- Tanks 8,11 and 12 first 14 day Proof of Performance Test commenced 13 January. Will prepare for second test commencing February.
- Fabrication of modified beach plate in process for DAF 1.
- DAF 7 entry halted due to chains being misaligned. Team working with Melbourne Water to assist with re-initiating access for works to continue. WAS header removal works in progress.

WTP 25W Lagoon Pond 1 HV and LV Renewals ~ F10461 |
- Install steelwork, formwork and pour stage 1 concrete at 48ZAB and 48ZCA MLC locations. Green cut concrete at 48ZAB and 48ZCA MLC locations.
- Remove formwork from aerator stands along North Rd.
- Install temporary generator connections at 48ZFA and 48ZFB MLCs.
- Rope conduits along South Rd.

Gardiners Creek Sewer Rehabilitation ~ Y10248 |
- Kick off meeting for legacy Art/Community project being undertaken in January.
- Minor omissions being completed.
- As Built drawings first draft completed being reviewed.

Maribyrnong Main Sewer Augmentation ~ P31258 |
- Shaft depth 31.7m.
- Shaft excavation is approx. 500mm above the Brighton Group sands and is below Ground Water level. Pressure Grouting underway to stabilise Brighton Group and facilitate installation of Spile Bars.
- Medway bulk earthworks to support receival shaft complete, continue with Churchill Drain crossing. Vegetation stripping pending Planning Permit Endorsement (MW resp).
- RFQ response for Bridge package due mid February.

Hoppers Crossing Pump Station 66kV ~ F10428 |
- Detailed design for the 80% design package is underway.
- The second day of the Risk Assessment / CHAZOP workshop for the OIU & PLC design was held on 18/01/2023. A third day for the workshop will be required to complete the outstanding nodes; scheduled for the 15 February.
- Tender packages currently under evaluation:
- Siemens HV CB for Switchboard
- Tender packages currently under negotiation:
- Dynamic Ratings (condition monitoring system package).
- Early works generator scope is underway. Load study and HV Circuit Breaker specification has been issued to Melbourne Water. Currently working on GA designs.