Bid Status
Project | Job | Value | Status |
---|---|---|---|
ETP Areas 15-26 Upgrades | F10730 | $22.4M | Submitted – Preferred Awaiting PN |
ETP Power Management Changes | H11894 | $482K | Submitted – Delayed |
WTP 55E Pond 1 MLC Renewal | F10427 | $14.9M | Won |
WTP HV Power & Energy Resilience ECI | Q03817 | $472K | Awaiting PN |
Refurb of Werribee Hanger 1 | Y05707 | $23M | Working |
Quarry Hill Tank | F10365 | $8M | Working |
Mordialloc Main Sewer Rehab | Y10341 | $6M | Working |
ETP Digester Upgrades | Y10286 | $70M | Working |
Thomson Dam Capacitor Upgrade | Y10364 | $3.5M | Working |
Tarago Fluoride Plant Upgrade | Y10209 | $10M | Working |
Project Delivery Update
North Yarra Main Relining Upper Section ~ Y10234 |
- Cleaning Section A (NYM128-119) completed.
- Lining of 3 sewer sections completed in section A. 230m of 450mmØ sewer with spiral PVC.
Tarago Fluoride Plant Upgrade ECI ~ Y10209 |
- ECI report submitted.
M76 Water Main Renewal ~ Q02707 |
- Pipelaying ongoing in High Street Road.
Essex Main Drain Renewal ~ Y10314 |
- Browning Walk –all 19 culverts installed.
Maribyrnong Main Sewer Augmentation ~ P31258 |
- Launch Shaft
- 398m complete (approx. 46%). Ground conditions are challenging resulting in a low TBM advance rate. Sticky clay conditions continue to block the TBM head resulting in increased downtime associated with manual clearing of the TBM head.
- Geotech sample testing for Particle Size Distribution, Moisture Content and Plasticity Index.
- Riverside:
- Direction Notice #1 – Site has been demobilised.
- Direction Notice #2: Siphon options assessment complete.
- HEC-RAS flood calibration report submitted.
Yan Yean WTP Upgrade~ Q04385 |
- Commissioning continues.
- Draft handover documentation submitted.
Yan Yean Pump Station ~ Q05322 |
- Mechanical installation continues in pump hall.
- ACR and associated Ausnet infrastructure completed.
- Electrical fitout continues.
- Underground discharge installation continues.
- RMU infrastructure installation in progress.
Yan Yean Bald Hill Pipeline ~ Q05333 |
- Productivities are improving.
- Overall works are 48% complete.
- Commissioning strategy agreed and commissioning plan submitted.
- Pipe install happening in SP1 – Grants Rd and SP2 – Paddock.
Hoppers Crossing Pump Station 66kV ~ F10428 |
- RMU offers have been received. Award is expected to be in January 2024.
- Powercor has completed their review; agreement has been reached between Powercor & SFP on 13/12/2023. Allowance will be made in the Melbourne Waster protection panels for interface with future.
- CE03 – Escalation Costs on Main Project delay due to Q03109. Approximately $536k. Submitted to Melbourne Water on 8 December.
WTP 25W Lagoon Pond 1 HV and LV Renewals ~ F10461 |
- Civil
- Back fill straight join excavation in roadway and reinstate area around 48XA06 kiosk.
- Electrical
- 48XA06 kiosk commissioned.
ETP HV-62A Switchboard & VH-LV Renewals ~ Y10307 (Q05103) |
- Works Completed on site, As Built documentation being finalised.
ETP Waste Activated Sludge ~ Q05102 |
- TWAS Pumps 8,11 and 12 internal wear parts replaced and DAF tanks operational 12 December.
- Pump performance testing completed. Report to be provided January 2024.
ETP Recuperative Thickener ~ Q05772 |
- Stage 1 achieved 30 November.
- Working through activities to achieve Stage 2