Bid Status

ProjectJobValueStatus
ETP Areas 15-26 UpgradesF10730$22.4MSubmitted – Preferred
Awaiting PN
ETP Power Management ChangesH11894$482KSubmitted – Delayed
WTP 55E Pond 1 MLC RenewalF10427$14.9MWon
WTP HV Power & Energy Resilience ECIQ03817$472KAwaiting PN
Refurb of Werribee Hanger 1Y05707$23MWorking
Quarry Hill TankF10365$8MWorking
Mordialloc Main Sewer RehabY10341$6MWorking
ETP Digester UpgradesY10286$70MWorking
Thomson Dam Capacitor UpgradeY10364$3.5MWorking
Tarago Fluoride Plant UpgradeY10209$10MWorking


Project Delivery Update

North Yarra Main Relining Upper Section ~ Y10234
  • Cleaning Section A (NYM128-119) completed.
  • Lining of 3 sewer sections completed in section A. 230m of 450mmØ sewer with spiral PVC.

Tarago Fluoride Plant Upgrade ECI ~ Y10209
  • ECI report submitted.
M76 Water Main Renewal ~ Q02707
  • Pipelaying ongoing in High Street Road.

Essex Main Drain Renewal ~ Y10314
  • Browning Walk –all 19 culverts installed.

Maribyrnong Main Sewer Augmentation ~ P31258
  • Launch Shaft
    • 398m complete (approx. 46%). Ground conditions are challenging resulting in a low TBM advance rate. Sticky clay conditions continue to block the TBM head resulting in increased downtime associated with manual clearing of the TBM head.
    • Geotech sample testing for Particle Size Distribution, Moisture Content and Plasticity Index.
  • Riverside:
    • Direction Notice #1 – Site has been demobilised.
    • Direction Notice #2: Siphon options assessment complete.
    • HEC-RAS flood calibration report submitted.
Yan Yean WTP Upgrade~ Q04385
  • Commissioning continues.
  • Draft handover documentation submitted.
Yan Yean Pump Station ~ Q05322
  • Mechanical installation continues in pump hall.
  • ACR and associated Ausnet infrastructure completed.
  • Electrical fitout continues.
  • Underground discharge installation continues.
  • RMU infrastructure installation in progress.
Yan Yean Bald Hill Pipeline ~ Q05333
  • Productivities are improving. 
  • Overall works are 48% complete.
  • Commissioning strategy agreed and commissioning plan submitted.
  • Pipe install happening in SP1 – Grants Rd and SP2 – Paddock.
Hoppers Crossing Pump Station 66kV ~ F10428
  • RMU offers have been received. Award is expected to be in January 2024.
  • Powercor has completed their review; agreement has been reached between Powercor & SFP on 13/12/2023. Allowance will be made in the Melbourne Waster protection panels for interface with future.
  • CE03 – Escalation Costs on Main Project delay due to Q03109. Approximately $536k. Submitted to Melbourne Water on 8 December.
WTP 25W Lagoon Pond 1 HV and LV Renewals ~ F10461
  • Civil
    • Back fill straight join excavation in roadway and reinstate area around 48XA06 kiosk.
  • Electrical
    • 48XA06 kiosk commissioned.
ETP HV-62A Switchboard & VH-LV Renewals ~ Y10307 (Q05103)
  • Works Completed on site, As Built documentation being finalised.
ETP Waste Activated Sludge ~ Q05102
  • TWAS Pumps 8,11 and 12 internal wear parts replaced and DAF tanks operational 12 December.
  • Pump performance testing completed. Report to be provided January 2024.
ETP Recuperative Thickener ~ Q05772
  • Stage 1 achieved 30 November.
  • Working through activities to achieve Stage 2