Bid Status

ProjectJobValueStatus
Hoppers Crossing Pump Station 66kVF10428$7.4MSubmitted
Mt Evelyn WTP (aka Silvan DRP)F10270$12M+Working


Project Delivery Update

Holden Reservoir M486 Inlet Pipeline SP1 & SP2~ Q03295
  • Stage 1 certificate due early April.
Yan Yean WTP Upgrade~ Q04385
  • Civil – backwash slab installation 50% complete. Completed removal of concrete lining in cast in header works in preparation for recoating.
  • Mechanical – install pipework in filter tanks. Installation of lime infrastructure. Installation in TWPS pump well. Commence planning for removal of backwash header works.
  • Electrical – fit out and rough in at alum/coag building, isolated transformer and removed mains supply. Completed decommissioning of switchroom.
  • Underground piping – install TWS feed pipework.
Yan Yean Pump Station ~ Q05322
  • Design development in progress on track for 30% design submission.
  • Day 1 readiness in progress.
Winneke Main Sub Station Switchboard Replacement ~ D10103
  • Design:
    • Civil IFC Package completed.
    • IFC secondary design package due this week.
  • Procurement:
    • RMU package – Order has been placed, ABB informed that there is a delay of two weeks. Melbourne Water has been informed about this and an early warning letter sent to Melbourne Water.
    • PLC package – Order has been placed.
    • HV Cables – Order has been placed.
    • FO Cables – Order will be placed this week.
  • Main Work Package
    • Stage 1 Completion achieved on 11 March. Currently working on Defects and hand over document.
ETP HV-62A Switchboard & VH-LV Renewals ~ Y10307 (Q05103)
  • Design:
    • Starting 62M
  • Procurement:
    • 62M and 54M CEs procurement in progress
  • Construction:
    • Installation of temporary 2 of 500kVA generator in area 92.
    • Removal of temporary generator in area 92.
    • 62HC bus outage completed.
    • Installation and commissioning of 4 new 6.6.kV circuit breakers in 62HC.
    • NDD and survey completed in area 72
    • 4M procurement  – PO for Tyree
    • CIG provided the close out documentation – pending review
    • All CEs approved by MW, total TCE 29.26M
ETP Recuperative Thickener ~ Q05772
  • Commissioning in progress.
  • Gearon – Road preparation completed. Asphalt works scheduled May 22
ETP Waste Activated Sludge ~ Q05102
  • Adx electrical – cable installation from 26MF to gallery. Continue terminating in 23MF switchboard.
  • AMS – WAS header installation 50% complete. Weir support brackets installation in tanks in progress.
  • Speedpro – completed concrete plinths and void filling works.

WTP Electrical Reliability Additional Works ~ F10133
  • Design:
    • IFC – design completed.
    • CE – The revised protection study completed. Currently being reviewed by Melbourne Water
  • Construction
    • Schneider LLI works scheduled for Jan 2022 finished. The last set of LLIs initially scheduled for April 2022 postponed until protection study is completed
    • ABB LLI works completed. 25W Blower Building SCADA works are in progress

WTP 25W Lagoon Pond 1 HV and LV Renewals ~ F10461
  • Design:
    • Civil IFC design is in progress.
    • Currently Downer is working on HV Design package.
  • Procurement:
    • MLC procurement – order has been placed.
    • RMU- Order has been placed.
    • In the process of finalising the HV Sub station procurement package.
    • HV Cable and PO cable orders have been placed..
  • Construction:
    • Civil construction works started on 26 April.
Gardiners Creek Sewer Rehabilitation ~ Y10248
  • Lining works commenced.
  • All lining materials ordered but the Covid impacts in China are delaying the CIPP materials delivery.
  • Penstock removal commenced and 50% complete.
  • CE submitted and expected to be approved.
  • Traversing sewer and bypass system to start shortly.

Maribyrnong Main Sewer Augmentation ~ P31258
  • JV Partner still working through methodology for shaft and tunnelling works regarding subby/self perform engagement and to advise SFP on IR methodology. Advised it will be by the end of the week.
  • Site preparations to begin excavation of launch shaft.
  • Preparation of construction work pack documentation for Maribyrnong river access tracks.
  • Commenced Hamstead Road and Willamson Road crossovers
  • Continued site preparation for site concrete access road. Planning to finalise concrete road pour next week.

Interlocking Safety Upgrades for HV Water Sites ~ Y10260
  • SE has requested SFP JV to take pictures of one of the key exchange boxes in Cardinia – Silvan to confirm the parts. Outage rescheduled to 5 May.
  • Upcoming Activities:
    • Completion of Project Management Documents.
    • Preparation of contract with SE for the installation works. 
    • Schneider Electric has provided date 6 May for the delivery  .
    • Visit Cardinia pumping station on 5 May for key exchange boxes inspection.