Bid Status
Project | Job | Value | Status |
---|---|---|---|
Hoppers Crossing Pump Station 66kV | F10428 | $7.4M | Submitted |
Mt Evelyn WTP (aka Silvan DRP) | F10270 | $12M+ | Working |
Project Delivery Update
Holden Reservoir M486 Inlet Pipeline SP1 & SP2~ Q03295 |
- Stage 1 certificate due early April.
Yan Yean WTP Upgrade~ Q04385 |
- Civil – backwash slab installation 50% complete. Completed removal of concrete lining in cast in header works in preparation for recoating.
- Mechanical – install pipework in filter tanks. Installation of lime infrastructure. Installation in TWPS pump well. Commence planning for removal of backwash header works.
- Electrical – fit out and rough in at alum/coag building, isolated transformer and removed mains supply. Completed decommissioning of switchroom.
- Underground piping – install TWS feed pipework.
Yan Yean Pump Station ~ Q05322 |
- Design development in progress on track for 30% design submission.
- Day 1 readiness in progress.
Winneke Main Sub Station Switchboard Replacement ~ D10103 |
- Design:
- Civil IFC Package completed.
- IFC secondary design package due this week.
- Procurement:
- RMU package – Order has been placed, ABB informed that there is a delay of two weeks. Melbourne Water has been informed about this and an early warning letter sent to Melbourne Water.
- PLC package – Order has been placed.
- HV Cables – Order has been placed.
- FO Cables – Order will be placed this week.
- Main Work Package
- Stage 1 Completion achieved on 11 March. Currently working on Defects and hand over document.
ETP HV-62A Switchboard & VH-LV Renewals ~ Y10307 (Q05103) |
- Design:
- Starting 62M
- Procurement:
- 62M and 54M CEs procurement in progress
- Construction:
- Installation of temporary 2 of 500kVA generator in area 92.
- Removal of temporary generator in area 92.
- 62HC bus outage completed.
- Installation and commissioning of 4 new 6.6.kV circuit breakers in 62HC.
- NDD and survey completed in area 72
- 4M procurement – PO for Tyree
- CIG provided the close out documentation – pending review
- All CEs approved by MW, total TCE 29.26M
ETP Recuperative Thickener ~ Q05772 |
- Commissioning in progress.
- Gearon – Road preparation completed. Asphalt works scheduled May 22
ETP Waste Activated Sludge ~ Q05102 |
- Adx electrical – cable installation from 26MF to gallery. Continue terminating in 23MF switchboard.
- AMS – WAS header installation 50% complete. Weir support brackets installation in tanks in progress.
- Speedpro – completed concrete plinths and void filling works.
WTP Electrical Reliability Additional Works ~ F10133 |
- Design:
- IFC – design completed.
- CE – The revised protection study completed. Currently being reviewed by Melbourne Water
- Construction
- Schneider LLI works scheduled for Jan 2022 finished. The last set of LLIs initially scheduled for April 2022 postponed until protection study is completed
- ABB LLI works completed. 25W Blower Building SCADA works are in progress
WTP 25W Lagoon Pond 1 HV and LV Renewals ~ F10461 |
- Design:
- Civil IFC design is in progress.
- Currently Downer is working on HV Design package.
- Procurement:
- MLC procurement – order has been placed.
- RMU- Order has been placed.
- In the process of finalising the HV Sub station procurement package.
- HV Cable and PO cable orders have been placed..
- Construction:
- Civil construction works started on 26 April.
Gardiners Creek Sewer Rehabilitation ~ Y10248 |
- Lining works commenced.
- All lining materials ordered but the Covid impacts in China are delaying the CIPP materials delivery.
- Penstock removal commenced and 50% complete.
- CE submitted and expected to be approved.
- Traversing sewer and bypass system to start shortly.
Maribyrnong Main Sewer Augmentation ~ P31258 |
- JV Partner still working through methodology for shaft and tunnelling works regarding subby/self perform engagement and to advise SFP on IR methodology. Advised it will be by the end of the week.
- Site preparations to begin excavation of launch shaft.
- Preparation of construction work pack documentation for Maribyrnong river access tracks.
- Commenced Hamstead Road and Willamson Road crossovers
- Continued site preparation for site concrete access road. Planning to finalise concrete road pour next week.
Interlocking Safety Upgrades for HV Water Sites ~ Y10260 |
- SE has requested SFP JV to take pictures of one of the key exchange boxes in Cardinia – Silvan to confirm the parts. Outage rescheduled to 5 May.
- Upcoming Activities:
- Completion of Project Management Documents.
- Preparation of contract with SE for the installation works.
- Schneider Electric has provided date 6 May for the delivery .
- Visit Cardinia pumping station on 5 May for key exchange boxes inspection.