Bid Status
Project | Job | Value | Status |
---|---|---|---|
Hoppers Crossing Pump Station 66kV | F10428 | $7.4M | Submitted |
Mt Evelyn WTP (aka Silvan DRP) | F10270 | $12M+ | Working |
Yan Yean Bald Hill Pipeline | Q05333 | $45.6M | Won |
Project Delivery Update
Holden Reservoir M486 Inlet Pipeline SP1 & SP2~ Q03295 |
- Stage 1 certificate due early April.
Yan Yean WTP Upgrade~ Q04385 |
- Civil – completion of FSA unloading bund, barometric loop slab and TWPS slab, commence backwash slab installation.
- Mechanical – install water reticulation in FSA building, TWPS pipe work to slab level, gas return pipe work, inlet pipe work.
- Electrical – fit out and rough in at alum/coag building, isolated MSB and commenced decommissioned of mcc ab and e.
- SFPJV – alkalinity cutover and proof of performance complete, cutover of power supply to generator completed.
- Underground piping – install backwash pipe work, commence removal of TWPS inlet pipe.
Yan Yean Pump Station ~ Q05322 |
- Completed kick-off meeting.
- Commencing project planning and design start-up.
Winneke Main Sub Station Switchboard Replacement ~ D10103 |
- Design:
- Civil 100% design package has been submitted to Melbourne Water.
- 80% secondary design package is in progress.
- Procurement:
- RMU package – Order has been placed, ABB informed that there is a delay of 2 weeks. MW has been informed about this and an early warning letter will be sent this week.
- PLC package – Order has been placed
- HV Cables – Order has been placed
- FO Cables – Order will be placed this week
- Main Work Package
- Stage 1 Completion achieved on 11th March
ETP HV-62A Switchboard & VH-LV Renewals ~ Y10307 (Q05103) |
- Design:
- Starting 62M
- Procurement:
- 62M and 54M CEs procurement in progress
- Construction:
- Continue cable hauling in new 62HA building
- Cable hauling via electrical ducts
- Control desk cable termination
- Civil works 62M contract – executed
- Generators for the first outage delivered
- All CEs approved by MW, total TCE 29.26M
ETP Recuperative Thickener IPPN Approved ~ Q05772 |
- AMES – cladding & lagging of pipework
- Chadoak – installation of sampling sinks, removal of walkway
- SFPJV – Commissioning in progress, RDTS and polymer system commissioning, preparation of handover documentation
- Gearon – Demobilised for final roadworks
ETP Waste Activated Sludge ~ Q05102 |
- Adx electrical – install cable management system, switchboards and cabling
- AMS – mark out and set out of brackets in tanks 8,11 and 12. Install brackets inside gallery
- SFPJV – install saturator tanks
WTP Electrical Reliability Additional Works ~ F10133 |
- Design:
- IFC – design completed.
- CE – the revised protection study design in progress.
- Construction:
- Schneider LLI works scheduled for Jan 2022 finished. The last set of LLIs initially scheduled for April 2022 postponed until protection study is completed.
- ABB LLI works are in progress. Schedule to finish by 8th April
WTP 25W Lagoon Pond 1 HV and LV Renewals ~ F10461 |
- Design:
- Civil IFC design is in progress.
- Currently Downer is working on HV Design package.
- Procurement:
- MLC procurement – order has been placed.
- RMU- Order has been placed.
- In the process of finalising the HV Sub station procurement package.
- AMES is selected as the Civil Subbie.
- Construction:
- Construction will begin on 26 April.
Gardiners Creek Sewer Rehabilitation ~ Y10248 |
- Lining works commenced.
- Some issues with installs at two of the lines, there were failures in the expansion.
- CIPP contract signed.
- Manhole modifications ongoing.
- Focus on lining in the upcoming months to June.
Maribyrnong Main Sewer Augmentation ~ P31258 |
- Concrete slab shaft and tunnel are completed.
- Slope stability issue on southern bank further Geotech required.
- Ring beam for shaft completed.
- Pipe supply contract final negotiations awaiting signatures.
Interlocking Safety Upgrades for HV Water Sites ~ Y10260 |
- Design:
- IFC design has been issued.
- Stantec engaged Downer EDI for design.
- Procurement:
- Interlock kits have been ordered, current lead time of 14-16 weeks, no impact to schedule at this stage.
- Currently arranging site visit to investigate existing key exchange box in Cardinia – Silvan Pumping station.
- Finance:
- Project in progress of setting up in PMR.