Bid Status

ProjectJobValueStatus
Hoppers Crossing Pump Station 66kVF10428$7.4MSubmitted
Mt Evelyn WTP (aka Silvan DRP)F10270$12M+Working
Yan Yean Bald Hill PipelineQ05333$45.6M Won


Project Delivery Update

Holden Reservoir M486 Inlet Pipeline SP1 & SP2~ Q03295
  • Stage 1 certificate due early April.
Yan Yean WTP Upgrade~ Q04385
  • Civil – completion of FSA unloading bund, barometric loop slab and TWPS slab, commence backwash slab installation.
  • Mechanical – install water reticulation in FSA building, TWPS pipe work to slab level, gas return pipe work, inlet pipe work.
  • Electrical – fit out and rough in at alum/coag building, isolated MSB and commenced decommissioned of mcc ab and e.
  • SFPJV – alkalinity cutover and proof of performance complete, cutover of power supply to generator completed.
  • Underground piping – install backwash pipe work, commence removal of TWPS inlet pipe.
Yan Yean Pump Station ~ Q05322
  • Completed kick-off meeting.
  • Commencing project planning and design start-up.
Winneke Main Sub Station Switchboard Replacement ~ D10103
  • Design:
    • Civil 100% design package has been submitted to Melbourne Water.
    • 80% secondary design package is in progress.
  • Procurement:
    • RMU package – Order has been placed, ABB informed that there is a delay of 2 weeks. MW has been informed about this and an early warning letter will be sent this week.
    • PLC package – Order has been placed
    • HV Cables – Order has been placed
    • FO Cables – Order will be placed this week
  • Main Work Package
    • Stage 1 Completion achieved on 11th March

ETP HV-62A Switchboard & VH-LV Renewals ~ Y10307 (Q05103)
  • Design:
    • Starting 62M
  • Procurement:
    • 62M and 54M CEs procurement in progress
  • Construction:
    • Continue cable hauling in new 62HA building
    • Cable hauling via electrical ducts
    • Control desk cable termination
    • Civil works 62M contract – executed
    • Generators for the first outage delivered
    • All CEs approved by MW, total TCE 29.26M

ETP Recuperative Thickener IPPN
Approved ~ Q05772
  • AMES – cladding & lagging of pipework
  • Chadoak – installation of sampling sinks, removal of walkway
  • SFPJV – Commissioning in progress, RDTS and polymer system commissioning, preparation of handover documentation
  • Gearon – Demobilised for final roadworks
ETP Waste Activated Sludge ~ Q05102
  • Adx electrical – install cable management system, switchboards and cabling
  • AMS – mark out and set out of brackets in tanks 8,11 and 12. Install brackets inside gallery
  • SFPJV – install saturator tanks

WTP Electrical Reliability Additional Works ~ F10133
  • Design:
    • IFC – design completed.
    • CE – the revised protection study design in progress.
  • Construction:
    • Schneider LLI works scheduled for Jan 2022 finished. The last set of LLIs initially scheduled for April 2022 postponed until protection study is completed.
    • ABB LLI works are in progress. Schedule to finish by 8th April

WTP 25W Lagoon Pond 1 HV and LV Renewals ~ F10461
  • Design:
    • Civil IFC design is in progress.
    • Currently Downer is working on HV Design package.
  • Procurement:
    • MLC procurement – order has been placed.
    • RMU- Order has been placed.
    • In the process of finalising the HV Sub station procurement package.
    • AMES is selected as the Civil  Subbie.
  • Construction:
    • Construction will begin on 26 April.
Gardiners Creek Sewer Rehabilitation ~ Y10248
  • Lining works commenced.
  • Some issues with installs at two of the lines, there were failures in the expansion.
  • CIPP contract signed.
  • Manhole modifications ongoing.
  • Focus on lining in the upcoming months to June.

Maribyrnong Main Sewer Augmentation ~ P31258
  • Concrete slab shaft and tunnel are completed.
  • Slope stability issue on southern bank further Geotech required.
  • Ring beam for shaft completed.
  • Pipe supply contract final negotiations awaiting signatures.

Interlocking Safety Upgrades for HV Water Sites ~ Y10260
  • Design:
    • IFC design has been issued.
    • Stantec engaged Downer EDI for design.
  • Procurement:
    • Interlock kits have been ordered, current lead time of 14-16 weeks, no impact to schedule at this stage.
    • Currently arranging site visit to investigate existing key exchange box in Cardinia – Silvan Pumping station.
  • Finance:
    • Project in progress of setting up in PMR.