Bid Status
Project | Job | Value | Status |
---|---|---|---|
Hoppers Crossing Pump Station 66kV | F10428 | $7.4M | Submitted |
Yan Yean Pump Station | Q05322 | $23.9M | Won |
Yan Yean Bald Hill Pipeline | Q05333 | $45.6M | Won |
Project Delivery Update
Holden Reservoir M486 Inlet Pipeline SP1 & SP2~ Q03295 |
- PC Stage 1 requested.
- Defects onsite re-restoration and LFI have been completed.
- ACC to undertake some further defect repairs prior to stage 1.
Yan Yean WTP Upgrade~ Q04385 |
- Civil works – TWPS concrete collar, barometric loop pile completed. Commence FSA unloading bund.
- Completed coating in FSA building.
- E&IC – installation of electrical conduits and cable management system. Alkalinity system cutover and SAT commenced.
- Mechanical – continue to fit out GAC return pipework and TWPS.
- Design deliverables for CE04 under internal review.
- Commenced Alkalinity system SAT. Issues encountered with existing CO2 system. Cutover works still on track as electrical pre-commissioning completed successfully.
- CE04 approval from under way – internal Melbourne Water approvals completed. Awaiting formal CE direction.
Winneke Main Sub Station Switchboard Replacement ~ D10103 |
- Design:
- Civil 100% design package has been submitted to Melbourne Water.
- 80% secondary design package is in progress.
- Procurement:
- RMU package – Order has been placed.
- PLC package – Order has been placed.
- HV Cables – Order has been placed.
- FO Cables – Order will be placed this week.
- Main Work Package:
- Commissioning completed.
- The final site walk through with Melbourne Water scheduled for 4 March.
ETP HV-62A Switchboard & VH-LV Renewals ~ Y10307 (Q05103) |
- Design:
- Starting 62M
- Procurement:
- 62M and 54M CEs procurement in progress
- Construction:
- Modification of steel work in 62HC for new CB installation.
- Primary testing of new CB’s in 62HC.
- Primary testing of VT’s in 62HA.
- Cable installation in 62HA.
- Earthing in 62HA.
- All CEs approved by MW, total TCE 29.26M
ETP Recuperative Thickener IPPN Approved ~ Q05772 |
- Tankweld/AMES – installation of pipework cladding.
- ADX Electrical – energization of switchroom achieved 9 February. Pre-commissioning and closeout of QA lots in progress.
- Electro80 – mobilised on site and commenced pre-commissioning.
- SFPJV – pre-commissioning 90% completed in RT building. Wet commissioning of 3W commenced.
- Bluefire and Royal Eagle – commissioning in progress.
- Austin Gardner (Project Engineer) commenced 21 February.
ETP Waste Activated Sludge ~ Q05102 |
- 95% of long lead procurement items have arrived on site (compressor outstanding).
- Hydrotesting of DAF tanks 8 and 11 completed.
- Mechanical fabrication of shutdown materials completed.
- Day 1 readiness review completed.
- Executed electrical installation contract.
- Execution of final mechanical installation works in progress.
WTP Electrical Reliability Additional Works ~ F10133 |
- Design:
- IFC – design completed.
- CE – the revised protection study design in progress.
- Construction:
- Schneider LLI works scheduled for January finished. The last set of LLIs are scheduled for April.
- Escutcheon works started.
- RMU cut over works started and final RMU commissioning works are now in progress.
- ABB LLI works are scheduled for mid March.
- Procurement:
- LLIs: ABB (x 21): Installation to begin in March.
WTP 25W Lagoon Pond 1 HV and LV Renewals ~ F10461 |
- Design:
- Civil 100% design package has been submitted to Melbourne Water.
- Currently Downer is working on the protection study. Cable sizing report and the fault current study report have been submitted to Melbourne Water.
- Procurement:
- MLC procurement – order has been placed.
- Quotes received for the RMU. Currently going through the technical evaluation. Aiming to place the order this week.
- Waiting for the HV Kiosk Substation quotes.
- In the process of finalising the Civil sub contractor. Currently 2 x sub contractors are short listed.
- Construction:
- Aiming to mobilise on site by end of March.
Gardiners Creek Sewer Rehabilitation ~ Y10248 |
- Some impacts to program – COVID impacted subbies.
- Manhole modifications commenced.
- Tree removal completed.
- Cleaning of lines ongoing.
- Mobilised to site office at Warrigal Rd and have it set up for use..
Maribyrnong Main Sewer Augmentation ~ P31258 |
- Shaft design complete:
- Access to DOT site granted and hoarding to be installed in January.
- Background noise modelling completed.
- WBS finalised, costs still to be loaded into JDE once final breakdown has been agreed with new Commercial Manager.
- Bridge subcontractors short listed and ECI process has commenced.
- Site office has been chosen, existing house on DOT site to be refurbished.
Interlocking Safety Upgrades for HV Water Sites ~ Y10260 |
- Design:
- IFC design has been issued.
- Stantec engaged Downer EDI for design.
- Procurement:
- Interlock kits have been ordered, current lead time of 14-16 weeks, no impact to schedule at this stage.
- Finance:
- Project in progress of setting up in PMR.