Bid Status

ProjectJobValueStatus
Hoppers Crossing Pump Station 66kVF10428$3.5MWorking
Yan Yean Pump StationQ05322$23.9MWon
Yan Yean Bald Hill PipelineQ05333$45.6M Won


Project Delivery Update

Hawthorn Main Sewer Rehabilitation~ P33546
  • Stage 2 Certificate Issued.

Holden Reservoir M486 Inlet Pipeline SP1 & SP2~ Q03295
  • PC Stage 1 requested.
  • Defects onsite re-restoration and LFI have been completed.
  • ACC to undertake some further defect repairs prior to stage 1.
REFCL Tranche 2 Electrical Compliance B Thompson Hydro ~ Y10219
  • Stage 2 Completion of the project has been achieved.

Yan Yean WTP Upgrade~ Q04385
  • Civil works – TWPS concrete collar installation and commenced surface preparation for floor coating in FSA building.
  • E&IC – installation of electrical conduits and cable management system.
  • Mechanical – Continue mechanical fit-out alum/poly dosing system. Commence mechanical installation of lime equipment
  • Design commenced for CE04 activities.
  • Alkalinity & TDU Commissioning Plan being finalized.
Lillydale Lake Wetland Rectification
Approved ~ Y10192
  • Stage 1 certificate received.
  • Awaiting Stage 2 certificate.

Winneke Main Sub Station Switchboard Replacement ~ D10103
  • Design
    • Downer has been engaged as the HV Design Subconsultant (through Stantec).
    • Finalising Civil 80% design package with revised trenching details.
    • Finalised comments from Melbourne Water for 30% HV design packages and HV kiosk IFT package.
  • Procurement
    • MLC Package: Trivantage is the preferred supplier. Currently pending approval from Melbourne Water on the revised aluminium construction of the MLCs.
    • RMU quotation received by Eaton, finalising the technical queries with Eaton. HV kiosks responses to be received by first week of February.
    • Finalised redline markups of revised trench layouts for civil RFT.

Youell Street Sewer Renewals ~ Q07136
  • Stage 2 certificate has been received.

ETP HV-62A Switchboard & VH-LV Renewals ~ Y10307 (Q05103)
  • Project is progressing well.
  • Continuation of cable tray within new building.
  • LV Cable hauling in the galleries.
  • Commissioning preparation on going.
  • Meeting with Synertec SCADA.
  • Control desk works progressing.

ETP Recuperative Thickener IPPN
Approved ~ Q05772
  • Tankweld/AMES – leak testing completed for piping in RT building. Continue closeout of punchlist items.
  • ADX Electrical – electrical installation of OCF equipment. Preparation for energization in February.
  • Electro80 – mobilized on site and commenced pre-commissioning.
  • SFPJV – HV cable installation completed. Terminations of HV cable and preparation for energization in February. Pre-commissioning commenced.
  • Bluefire & Royal Eagle – on site installation.
ETP Waste Activated Sludge ~ Q05102
  • Rectification of leaks in Tanks 11 and 12 in progress.
  • Continue delivery of equipment on site.
  • Electrical and mechanical installation contract execution in progress.

WTP Electrical Reliability Additional Works ~ F10133
  • Design:
    • IFC – Design completed
  • Construction:
    • Schneider LLI works scheduled for January finished. The last set of LLIs are scheduled for April.
    • Escutcheon works started.
    • RMU Cut over works to be started in February.
    • 55E Lagoon Construction works completed. Live Line Indicators and Earth Switch indication at 43XA01 Kiosk pending.
  • Procurement:
    • Eaton – 3 x RMU’s: Received.
    • LLIs: ABB (x 21): Installation to begin in March.

WTP 25W Lagoon Pond 1 HV and LV Renewals ~ F10461
  • Design:
    • Downer has been engaged as the HV Design Subconsultant (through Stantec).
    • Finalising Civil 100% design package, completed CHAIR meeting for Civil works.
    • Downer currently working on the protection study.
  • Procurement:
    • Waiting for the final approval from SFPJV board for the procurement of the MLCs.
    • Quotes received for the RMU. Currently going through the technical evaluation.
    • Waiting for the HV Kiosk Substation quotes.
    • Waiting for the offers for the Civil Package RFT.
Gardiners Creek Sewer Rehabilitation ~ Y10248
  • Some impacts to program – Covid impacted subbies.
  • Manhole modifications commenced.
  • Tree removal completed.
  • Cleaning of lines ongoing.
  • Mobilised to site office at Warrigal Road and have it set up ready for use.

Maribyrnong Main Sewer Augmentation ~ P31258
  • Shaft design complete:
    • Access to DOT site granted and hoarding to be installed in January.
    • Background noise modelling completed.
    • WBS finalised, costs still to be loaded into JDE once final breakdown has been agreed with new Commercial Manager.
    • Bridge subcontractors short listed and ECI process has commenced.
    • Site office has been chosen, existing house on DOT site to be refurbished.

Interlocking Safety Upgrades for HV Water Sites ~ Y10260
  • Design:
    • IFC design has been issued.
    • Stantec engaged Downer EDI for design.
  • Procurement:
    • Finalised quotation with Schneider Electric (SE). Issued purchase order for the interlock kits. 
  • Finance:
    • Project in progress of setting up in PMR.