Bid Status
Project | Job | Value | Status |
---|---|---|---|
Hoppers Crossing Pump Station 66kV | F10428 | $3.5M | Working |
Yan Yean Pump Station | Q05322 | $23.9M | Won |
Yan Yean Bald Hill Pipeline | Q05333 | $45.6M | Won |
Project Delivery Update
Hawthorn Main Sewer Rehabilitation~ P33546 |
- Stage 2 Certificate Issued.
Holden Reservoir M486 Inlet Pipeline SP1 & SP2~ Q03295 |
- PC Stage 1 requested.
- Defects onsite re-restoration and LFI have been completed.
- ACC to undertake some further defect repairs prior to stage 1.
REFCL Tranche 2 Electrical Compliance B Thompson Hydro ~ Y10219 |
- Stage 2 Completion of the project has been achieved.
Yan Yean WTP Upgrade~ Q04385 |
- Civil works – TWPS concrete collar installation and commenced surface preparation for floor coating in FSA building.
- E&IC – installation of electrical conduits and cable management system.
- Mechanical – Continue mechanical fit-out alum/poly dosing system. Commence mechanical installation of lime equipment
- Design commenced for CE04 activities.
- Alkalinity & TDU Commissioning Plan being finalized.
Lillydale Lake Wetland Rectification Approved ~ Y10192 |
- Stage 1 certificate received.
- Awaiting Stage 2 certificate.
Winneke Main Sub Station Switchboard Replacement ~ D10103 |
- Design
- Downer has been engaged as the HV Design Subconsultant (through Stantec).
- Finalising Civil 80% design package with revised trenching details.
- Finalised comments from Melbourne Water for 30% HV design packages and HV kiosk IFT package.
- Procurement
- MLC Package: Trivantage is the preferred supplier. Currently pending approval from Melbourne Water on the revised aluminium construction of the MLCs.
- RMU quotation received by Eaton, finalising the technical queries with Eaton. HV kiosks responses to be received by first week of February.
- Finalised redline markups of revised trench layouts for civil RFT.
Youell Street Sewer Renewals ~ Q07136 |
- Stage 2 certificate has been received.
ETP HV-62A Switchboard & VH-LV Renewals ~ Y10307 (Q05103) |
- Project is progressing well.
- Continuation of cable tray within new building.
- LV Cable hauling in the galleries.
- Commissioning preparation on going.
- Meeting with Synertec SCADA.
- Control desk works progressing.
ETP Recuperative Thickener IPPN Approved ~ Q05772 |
- Tankweld/AMES – leak testing completed for piping in RT building. Continue closeout of punchlist items.
- ADX Electrical – electrical installation of OCF equipment. Preparation for energization in February.
- Electro80 – mobilized on site and commenced pre-commissioning.
- SFPJV – HV cable installation completed. Terminations of HV cable and preparation for energization in February. Pre-commissioning commenced.
- Bluefire & Royal Eagle – on site installation.
ETP Waste Activated Sludge ~ Q05102 |
- Rectification of leaks in Tanks 11 and 12 in progress.
- Continue delivery of equipment on site.
- Electrical and mechanical installation contract execution in progress.
WTP Electrical Reliability Additional Works ~ F10133 |
- Design:
- IFC – Design completed
- Construction:
- Schneider LLI works scheduled for January finished. The last set of LLIs are scheduled for April.
- Escutcheon works started.
- RMU Cut over works to be started in February.
- 55E Lagoon Construction works completed. Live Line Indicators and Earth Switch indication at 43XA01 Kiosk pending.
- Procurement:
- Eaton – 3 x RMU’s: Received.
- LLIs: ABB (x 21): Installation to begin in March.
WTP 25W Lagoon Pond 1 HV and LV Renewals ~ F10461 |
- Design:
- Downer has been engaged as the HV Design Subconsultant (through Stantec).
- Finalising Civil 100% design package, completed CHAIR meeting for Civil works.
- Downer currently working on the protection study.
- Procurement:
- Waiting for the final approval from SFPJV board for the procurement of the MLCs.
- Quotes received for the RMU. Currently going through the technical evaluation.
- Waiting for the HV Kiosk Substation quotes.
- Waiting for the offers for the Civil Package RFT.
Gardiners Creek Sewer Rehabilitation ~ Y10248 |
- Some impacts to program – Covid impacted subbies.
- Manhole modifications commenced.
- Tree removal completed.
- Cleaning of lines ongoing.
- Mobilised to site office at Warrigal Road and have it set up ready for use.
Maribyrnong Main Sewer Augmentation ~ P31258 |
- Shaft design complete:
- Access to DOT site granted and hoarding to be installed in January.
- Background noise modelling completed.
- WBS finalised, costs still to be loaded into JDE once final breakdown has been agreed with new Commercial Manager.
- Bridge subcontractors short listed and ECI process has commenced.
- Site office has been chosen, existing house on DOT site to be refurbished.
Interlocking Safety Upgrades for HV Water Sites ~ Y10260 |
- Design:
- IFC design has been issued.
- Stantec engaged Downer EDI for design.
- Procurement:
- Finalised quotation with Schneider Electric (SE). Issued purchase order for the interlock kits.
- Finance:
- Project in progress of setting up in PMR.