Bid Status

ProjectJobValueStatus
Hoppers Crossing Pump Station 66kVF10428$3.5MWorking
Yan Yean Pump StationQ05322$23.9MSubmitted
Winneke Treatment Plant – UV Disinfection SystemQ03309$44.3M Lost
Yan Yean Bald Hill PipelineQ05333$45.6M Submitted


Project Delivery Update

Hawthorn Main Sewer Rehabilitation~ P33546
  • Stage 2 Certificate Issued.

Holden Reservoir M486 Inlet Pipeline SP1 & SP2~ Q03295
  • PC Stage 1 requested.
  • Defects onsite re-restoration and LFI have been completed.
  • Awaiting Melbourne Water to issue Stage 1.
REFCL Tranche 2 Electrical Compliance B Thompson Hydro ~ Y10219
  • Stage 2 Completion of the project has been achieved.

Yan Yean WTP Upgrade~ Q04385
  • Civil works – Lime building modifications completed. Backwash tanks screed completed. Barometric loop preparation works 50% complete.
  • E&IC – TWS cutover completed.
  • Mechanical – installation of Delay Tank stairs completed. Continue mechanical fit-out alum/poly dosing system.
  • Design commenced for CE04 activities.
  • Harshana (Prasad) Dharmasena (Project Engineer – Mechanical) commenced onsite.
Lillydale Lake Wetland Rectification
Approved ~ Y10192
  • Stage 1 certificate received.
  • Awaiting Stage 2 certificate.

Winneke Main Sub Station Switchboard Replacement ~ D10103
  • All the design deliverables have been finalised and the long lead time materials have been procured.
  • CE0001 – Solar Works Change Event – Currently finalising ABB Primary and Schematic Drawings. Procurement of HV cables in progress.
  • In progress of secondary testing and protection relays programming on 11kV BUS B. Hi pot test scheduled for 11 and 12 January. On track to commission 11kV BUS B on 19 January.
  • In progress of fire system install (Blufire system) works, installing the new fire control panel.

Youell Street Sewer Renewals ~ Q07136
  • Stage 2 certificate has been received.

ETP HV-62A Switchboard & VH-LV Renewals ~ Y10307 (Q05103)
  • Project is progressing well.
  • Continuation of cable tray within new building.
  • Fire detection system installation.
  • Transformer encloser earthing of fence.
  • Site clean-up in readiness.
  • Cable hauling pit lid installation.
  • A meeting was held between MW Ops and SFPJV to finalise the Commissioning Plan.

ETP Recuperative Thickener IPPN
Approved ~ Q05772
  • AMES – completed Northern SDP pipework construction works.
  • Chadoak – all underground pipework completed.
  • Tankweld/AMES – finalizing fit-out in RT building and gallery 52 and 53 pipework. Leak testing completed in Polymer Building and Gallery 52 and 53.
  • ADX Electrical – continue installation of cables, terminations in LV building, RT building and Polymer building. Systems ready for energization in January.
  • Electro80 – preparation to mobilize to site for commissioning January.
  • SFPJV – installation of additional draw pits in preparation for pulling of HV cable pull.
  • Bluefire and Royal Eagle – on site installation.
ETP Waste Activated Sludge ~ Q05102
  • Concrete repair works complete in tanks 8, 11 and 12.
  • Continue delivery of equipment onsite.
  • FAT completed on switchboard.

WTP Electrical Reliability Additional Works ~ F10133
  • Design:
    • IFC – Design completed
  • Construction:
    • Schneider LLI works started. The works will be completed end of January.
    • Escutcheon works to be started third week of January.
    • RMU Cut over works to be started in February.
    • 55E Lagoon Construction works completed. Live Line Indicators and Earth Switch indication at 43XA01 Kiosk pending.
  • Procurement:
    • Eaton – 3 x RMU’s: Received.
    • LLIs: ABB (x 21): Installation to begin in February.

WTP 25W Lagoon Pond 1 HV and LV Renewals ~ F10461
  • Design:
    • Downer has been engaged as the HV Design Subconsultant (through Stantec).
    • Finalising Civil 80% design package, completed CHAIR meeting for Civil works.
    • Finalised comments from MW for 30% HV design packages and HV kiosk IFT package.
  • Procurement:
    • Quotes received for MLC package. Currently the evaluation is in progress. High level review indicated that there is a cost overrun associated with this package.
    • RFT sent for HV Kiosk and RMU. Quotes to be received end of January.
    • Civil Package RFT to be sent today.
Gardiners Creek Sewer Rehabilitation ~ Y10248
  • Lease for new office completed.
  • Site works commenced.
  • Mandate and Board have been finalised.
  • Spiralline material orders placed and contract signed.
  • CIPP materials and contract in draft with supplier for review.

Maribyrnong Main Sewer Augmentation ~ P31258
  • Shaft design complete:
    • Access to DOT site granted and hoarding to be installed in January.
    • Background noise modelling completed.
    • WBS finalised, costs still to be loaded into JDE once final breakdown has been agreed with new Commercial Manager.
    • Bridge subcontractors short listed and ECI process has commenced.
    • Site office has been chosen, existing house on DOT site to be refurbished.

Interlocking Safety Upgrades for HV Water Sites ~ Y10260
  • Design:
    • IFC design has been issued.
    • Stantec engaged Downer EDI for design.
  • Procurement:
    • Currently working with Schneider Electric (SE) to finalise quotation to procure the interlocks. 
  • Finance:
    • Project in progress of setting up in PMR.