Bid Status

ProjectJobValueStatus
Hoppers Crossing Pump Station 66kVF10424$3.5MWorking
Yan Yean Pump StationQ05322$23.9MSubmitted
Winneke Treatment Plant – UV Disinfection SystemQ03309$44.3M Submitted
Yan Yean Bald Hill PipelineQ05333$45.6M Submitted
M22 and M46 Main ReplacementQ02539$43.7MNot Preferred


Project Delivery Update

Hawthorn Main Sewer Rehabilitation~ P33546
  • Stage 2 Certificate Issued.

Holden Reservoir M486 Inlet Pipeline SP1 & SP2~ Q03295
  • PC stage 1 requested, awaiting Melbourne Water’s response.
  • In process of finalising drawings and completing some outstanding defects.
REFCL Tranche 2 Electrical Compliance B Thompson Hydro ~ Y10219
  • Stage 2 completion date achieved on 16 July.
  • Separable Portion 3 issued at of October.

Yan Yean WTP Upgrade~ Q04385
  • Civil works – delay tank modification, alum/poly unloading bund construction, alum bund modifications
  • E&IC – preparation works for cutover (generator, temporary panels, relocation of essential services)
  • Underground pipework – completion of line F & G, drainage at lime and FSA building
  • Mechanical – delivery of pipework for re-lift PS, delay tank, backwash pump station and filter transfer. Continue mechanical fit-out
  • Preparation for TWS and alkalinity system FAT and SAT
Lillydale Lake Wetland Rectification
Approved ~ Y10192
  • Works completed for Stage 1 completion
  • Awaiting Stage 1 certificate from Melbourne Water.

Winneke Main Sub Station Switchboard Replacement ~ D10103
  • All the design deliverables have been finalised and the long lead time materials have been procured.
  • 11kV Bus A works have been completed.
  • CE0001 – Solar Works Change Event – Melbourne Water has approved the full change event. The design works have been commenced. The RMU 143 and 141 Specs have been finalised and order has been placed with ABB.
  • New 11kV BUS B installation works have commenced.
  • Civil works associated with the 11kV BUS B core holes are complete. Painting of the switch room in progress.
  • The additional generator cost from Aggreko for the plant wide outage works has been received and change event was submitted to Melbourne Water for approval (CE07).

Youell Street Sewer Renewals ~ Q07136
  • Stage 1 achieved.
  • On track for Stage 2 in mid November, awaiting approval of submitted drawings.
  • Defects have been rectified.

ETP HV-62A Switchboard & VH-LV Renewals ~ Y10307 (Q05103)
  • Civil Infrastructure Group (CIG) have completed:
    • Commenced hanging fire rated plaster ceilings.
    • Connection of conduits from existing 62HB building.
    • Excavation works for the TEX foundation.
    • Conduit connection from Alan Bird Drive conduit bank to new building.
  • CE 02, 05, 06, 07, 08 and10 approved.
  • ABB FAT in progress; expected delivery first week of November.
  • CE 09, CE14, CE015 and CE16 submitted.

ETP Recuperative Thickener IPPN
Approved ~ Q05772
  • AMES – completing demobilisation/remediation of Northern SDP pipework.
  • Chadoak – preparation for 1W tie-in.
  • Tankweld/AMES – continue fit-out in RT building and gallery 52 and 53 pipework.
  • ADX Electrical – continue installation of cables, cable management and terminations in LV building, RT building and Polymer building.
  • CLQA – loaded carbon and catalytic iron media. Completing mechanical installation.
  • Delfab – installation of OCF platform.
  • Electro80 – continue PLC programming and internal FAT testing. Completed power plant testing.
  • SFPJV – preparation of HV circuit breaker shutdown installation.
  • Bluefire and Royal Eagle – on site installation.
ETP Waste Activated Sludge ~ Q05102
  • Concrete repairs 80% complete in tanks 8, 11 and 12.
  • Commencement of delivery of equipment on site.
  • Mobilisation of site compound complete.
  • IFC design development in progress.

WTP Electrical Reliability Additional Works ~ F10133
  • Design:
    • IFC – primary and secondary design drawing completed.
    • Comments received from Melbourne Water for this IFC Control Narrative.
  • Construction:
    • 55E Lagoon construction works completed. Live line indicators and earth switch indication at 55XA01 Kiosk pending.
    • 49ZHA pre-commissioned at site compound and mounted in the field.
    • Fibre works completed at 55QS09, 55E to 115E PS, 105W and 49ZHA.
    • ERW5 RMU control panel Stage 6 cutover completed.
  • Procurement:
    • Eaton – 3 x RMU’s, estimated delivery date, 17 November.
    • LLI’s: ABB (x 21) – installation to begin in December.
    • Schneider (x 14) – installation to begin in November.
WTP 25W Lagoon Pond 1 HV and LV Renewals ~ F10461
  • Financial system set up is in progress – PMR will be used for financial reporting.
  • Design:
    • Downer has been engaged at the HV Design Subconsultant (through Stantec).
    • MLC IFT package finalisation is in progress.
    • 30% Civil Drawing package has been submitted to Melbourne Water for review.

Gardiners Creek Sewer Rehabilitation ~ Y10248
  • Project kick off completed, WBS finalised and project team planning to commence works in November.
  • Working on acquiring a lease for the project office.
  • Mandate and Board to be finalised.

Maribyrnong Main Sewer Augmentation ~ P31258
  • Design commenced, key design subconsultants selected and engaged.
  • DoT land access to jack shaft compound now available.
  • Background noise modelling about to commence.
  • WBS finalised.
  • Day 1 readiness to be reviewed in November.
  • Mandate and Board to be finalised.