Bid Status
Project | Job | Value | Status |
---|---|---|---|
Hoppers Crossing Pump Station 66kV | F10424 | $3.5M | Working |
Yan Yean Pump Station | Q05322 | $23.9M | Submitted |
Winneke Treatment Plant – UV Disinfection System | Q03309 | $44.3M | Submitted |
Yan Yean Bald Hill Pipeline | Q05333 | $45.6M | Submitted |
M22 and M46 Main Replacement | Q02539 | $43.7M | Not Preferred |
Project Delivery Update
Hawthorn Main Sewer Rehabilitation~ P33546 |
- Stage 2 Certificate Issued.
Holden Reservoir M486 Inlet Pipeline SP1 & SP2~ Q03295 |
- PC stage 1 requested, awaiting Melbourne Water’s response.
- In process of finalising drawings and completing some outstanding defects.
REFCL Tranche 2 Electrical Compliance B Thompson Hydro ~ Y10219 |
- Stage 2 completion date achieved on 16 July.
- Separable Portion 3 issued at of October.
Yan Yean WTP Upgrade~ Q04385 |
- Civil works – delay tank modification, alum/poly unloading bund construction, alum bund modifications
- E&IC – preparation works for cutover (generator, temporary panels, relocation of essential services)
- Underground pipework – completion of line F & G, drainage at lime and FSA building
- Mechanical – delivery of pipework for re-lift PS, delay tank, backwash pump station and filter transfer. Continue mechanical fit-out
- Preparation for TWS and alkalinity system FAT and SAT
Lillydale Lake Wetland Rectification Approved ~ Y10192 |
- Works completed for Stage 1 completion
- Awaiting Stage 1 certificate from Melbourne Water.
Winneke Main Sub Station Switchboard Replacement ~ D10103 |
- All the design deliverables have been finalised and the long lead time materials have been procured.
- 11kV Bus A works have been completed.
- CE0001 – Solar Works Change Event – Melbourne Water has approved the full change event. The design works have been commenced. The RMU 143 and 141 Specs have been finalised and order has been placed with ABB.
- New 11kV BUS B installation works have commenced.
- Civil works associated with the 11kV BUS B core holes are complete. Painting of the switch room in progress.
- The additional generator cost from Aggreko for the plant wide outage works has been received and change event was submitted to Melbourne Water for approval (CE07).
Youell Street Sewer Renewals ~ Q07136 |
- Stage 1 achieved.
- On track for Stage 2 in mid November, awaiting approval of submitted drawings.
- Defects have been rectified.
ETP HV-62A Switchboard & VH-LV Renewals ~ Y10307 (Q05103) |
- Civil Infrastructure Group (CIG) have completed:
- Commenced hanging fire rated plaster ceilings.
- Connection of conduits from existing 62HB building.
- Excavation works for the TEX foundation.
- Conduit connection from Alan Bird Drive conduit bank to new building.
- CE 02, 05, 06, 07, 08 and10 approved.
- ABB FAT in progress; expected delivery first week of November.
- CE 09, CE14, CE015 and CE16 submitted.
ETP Recuperative Thickener IPPN Approved ~ Q05772 |
- AMES – completing demobilisation/remediation of Northern SDP pipework.
- Chadoak – preparation for 1W tie-in.
- Tankweld/AMES – continue fit-out in RT building and gallery 52 and 53 pipework.
- ADX Electrical – continue installation of cables, cable management and terminations in LV building, RT building and Polymer building.
- CLQA – loaded carbon and catalytic iron media. Completing mechanical installation.
- Delfab – installation of OCF platform.
- Electro80 – continue PLC programming and internal FAT testing. Completed power plant testing.
- SFPJV – preparation of HV circuit breaker shutdown installation.
- Bluefire and Royal Eagle – on site installation.
ETP Waste Activated Sludge ~ Q05102 |
- Concrete repairs 80% complete in tanks 8, 11 and 12.
- Commencement of delivery of equipment on site.
- Mobilisation of site compound complete.
- IFC design development in progress.
WTP Electrical Reliability Additional Works ~ F10133 |
- Design:
- IFC – primary and secondary design drawing completed.
- Comments received from Melbourne Water for this IFC Control Narrative.
- Construction:
- 55E Lagoon construction works completed. Live line indicators and earth switch indication at 55XA01 Kiosk pending.
- 49ZHA pre-commissioned at site compound and mounted in the field.
- Fibre works completed at 55QS09, 55E to 115E PS, 105W and 49ZHA.
- ERW5 RMU control panel Stage 6 cutover completed.
- Procurement:
- Eaton – 3 x RMU’s, estimated delivery date, 17 November.
- LLI’s: ABB (x 21) – installation to begin in December.
- Schneider (x 14) – installation to begin in November.
WTP 25W Lagoon Pond 1 HV and LV Renewals ~ F10461 |
- Financial system set up is in progress – PMR will be used for financial reporting.
- Design:
- Downer has been engaged at the HV Design Subconsultant (through Stantec).
- MLC IFT package finalisation is in progress.
- 30% Civil Drawing package has been submitted to Melbourne Water for review.
Gardiners Creek Sewer Rehabilitation ~ Y10248 |
- Project kick off completed, WBS finalised and project team planning to commence works in November.
- Working on acquiring a lease for the project office.
- Mandate and Board to be finalised.
Maribyrnong Main Sewer Augmentation ~ P31258 |
- Design commenced, key design subconsultants selected and engaged.
- DoT land access to jack shaft compound now available.
- Background noise modelling about to commence.
- WBS finalised.
- Day 1 readiness to be reviewed in November.
- Mandate and Board to be finalised.