Bid Status
Project | Job | Value | Status |
---|---|---|---|
Yan Yean Pump Station | Q05322 | $20M | Working |
Winneke Treatment Plant – UV Disinfection System | Q03309 | $40M | Working |
Yan Yean Bald Hill Pipeline | Q05333 | $30M | Working |
M22 and M46 Main Replacement | Q02539 | $43.7M | Submitted |
Gardiners Creek Main Sewer Rehabilitation | Y10248 | $12.3M | Won |
Maribyrnong Main Sewer Augmentation | P31258 | $55.2M | Won |
Project Delivery Update
Hawthorn Main Sewer Rehabilitation~ P33546 |
- SFPJV have completed all tasks and actions for Stage 2 Certificate to be issued start of October 2021.
Holden Reservoir M486 Inlet Pipeline SP1 & SP2~ Q03295 |
- Final restorations completed, LFI / EPR works completed early October, PC 1 anticipated end of October 2021.
- One outstanding Change Event for M333 Connection issued submitted to Melbourne Water. Follow up and close out expected by end of October 2021.
REFCL Tranche 2 Electrical Compliance B Thompson Hydro ~ Y10219 |
- Stage 2 completion date achieved on 16 July, 5021.
- Separable Portion 3 to be issued start of October 2021.
Yan Yean WTP Upgrade~ Q04385 |
- Electrical:
- Lime building cable tray and VSD installation.
- Preparation works for cutover (generator, temporary panels and DBs).
- Civil:
- TWPS and backwash tank waterproofing.
- Demolition in lime building.
- Modification works in lime building.
- Underground pipework:
- Completing Line E above ground connections.
- Drainage pit installation.
- Mechanical:
- External chemical dosing works around the lime building and across the bridge, installing poly vac unit and hoppers inside chemical room.
- Install filter to waste lines.
- Demo on west side of backwash tank.
Lillydale Lake Wetland Rectification Approved ~ Y10192 |
- Topsoil is being placed is at 90%.
- Site classed as non-essential by Melbourne Water and thus has been stood down until Restrictions are lifted.
Winneke Main Sub Station Switchboard Replacement ~ D10103 |
- All the design deliverables have been finalised and all the long lead time materials have been procured.
- 11kV Bus A outage currently ongoing, delay in testing due to weather on Yering Gorge feeder last Thursday, expected completion this Friday.
- DC and AC board cutover completed.
- 66kV CT and VT commissioned.
- All Change Events are approved except CE01 – Solar works. The revised CE was submitted to Melbourne Water and waiting for their approval.
Youell Street Sewer Renewals ~ Q07136 |
- Stage 1 achieved and all Omissions and Outstanding items of work completed.
- A final technical memo to be produced detailing compliance of the liner.
- Currently working on As- built Drawings.
- No Change Events raised on the Project.
ETP HV-62A Switchboard & VH-LV Renewals ~ Y10307 (Q05103) |
- Civil Infrastructure Group (CIG) have completed:
- Complete pre-cast panel installation
- Structural steel roof completed
- Temporary props removed
- Roof access and edge protection installed
- Reinstate completed areas on conduit route
- RECUP second feeder variation – CE10 submitted to Melbourne Water on Wed 11 August.
- ABB FAT postponed due to fire in the factory, early warning submitted to Melbourne Water, update officially submitted through ASITE.
- CE 11, CE12 and CE13 submitted.
ETP Recuperative Thickener IPPN Approved ~ Q05772 |
- AMES – commenced preparation for North SDP pipework tie-in scheduled Oct 2021.
- Chadoak – installation of fire water in RT.
- Tankweld/AMES – completed mechanical installation in wet polymer area. Continue mechanical fitout in RT building. Continue pipework decommissioning and preparation works for gallery pipework.
- ADX Electrical – continue installation of cable management infrastructure in LV building, RT building and Polymer building.
- CLQA – mobilized and works in progress.
- Trivantage – switchboards installed on site.
- Electro80 – continue PLC programming and preparation for 62HC breaker commissioning.
- SFPJV – HV infrastructure installation in progress.
ETP Waste Activated Sludge ~ Q05102 |
- Scaffold access installed in tanks 8, 11 and 12.
- Preparation of mobilisation of Mattioli for concrete repair works.
- Procurement of major equipment continues (electrical installation, mechanical installation, valves, instruments, scraper system).
- IFC design development in progress.
WTP Electrical Reliability Additional Works ~ F10133 |
- 55E Lagoon control panel installation works have started.
- The construction and commissioning plan for 55E Lagoon works has been finalised.
- SFP JV received approval for CE13 – WTP25W SCADA Modification Works.
- Procurement – waiting for delivery of 3 x RMUs from Eaton, 3 x Control Boxes from Electro80 and LLIs from Schneider. The contracts with ABB and Schneider for the supply and installation of LLI have been finalised.
WTP 25W Lagoon Pond 1 HV and LV Renewals ~ F10461 |
- Financial set up in progress.
- Design kick-off.