Project Delivery Update

Hawthorn Main Sewer Rehabilitation~ P33546
  • SFPJV have completed all tasks and actions for Stage 2 Certificate to be issued start of October 2021.
Holden Reservoir M486 Inlet Pipeline SP1 & SP2~ Q03295
  • Final restorations completed, LFI / EPR works completed early October, PC 1 anticipated end of October 2021.
  • One outstanding Change Event for M333 Connection issued submitted to Melbourne Water. Follow up and close out expected by end of October 2021.
REFCL Tranche 2 Electrical Compliance B Thompson Hydro ~ Y10219
  • Stage 2 completion date achieved on 16 July, 5021.
  • Separable Portion 3 to be issued start of October 2021.
Yan Yean WTP Upgrade~ Q04385
  • Electrical:
    • Lime building cable tray and VSD installation.
    • Preparation works for cutover (generator, temporary panels and DBs).
  • Civil:
    • TWPS and backwash tank waterproofing.
    • Demolition in lime building.
    • Modification works in lime building.
  • Underground pipework:
    • Completing Line E above ground connections.
    • Drainage pit installation.
  • Mechanical:
    • External chemical dosing works around the lime building and across the bridge, installing poly vac unit and hoppers inside chemical room.
    • Install filter to waste lines.
    • Demo on west side of backwash tank.
Lillydale Lake Wetland Rectification
Approved ~ Y10192
  • Topsoil is being placed is at 90%.
  • Site classed as non-essential by Melbourne Water and thus has been stood down until Restrictions are lifted.

Winneke Main Sub Station Switchboard Replacement ~ D10103
  • All the design deliverables have been finalised and all the long lead time materials have been procured.
  • 11kV Bus A outage currently ongoing, delay in testing due to weather on Yering Gorge feeder last Thursday, expected completion this Friday.
  • DC and AC board cutover completed.
  • 66kV CT and VT commissioned.
  • All Change Events are approved except CE01 – Solar works. The revised CE was submitted to Melbourne Water and waiting for their approval.
Youell Street Sewer Renewals ~ Q07136
  • Stage 1 achieved and all Omissions and Outstanding items of work completed.
  • A final technical memo to be produced detailing compliance of the liner.
  • Currently working on As- built Drawings.
  • No Change Events raised on the Project.

ETP HV-62A Switchboard & VH-LV Renewals ~ Y10307 (Q05103)
  • Civil Infrastructure Group (CIG) have completed:
    • Complete pre-cast panel installation
    • Structural steel roof completed
    • Temporary props removed
    • Roof access and edge protection installed
    • Reinstate completed areas on conduit route
  • RECUP second feeder variation – CE10 submitted to Melbourne Water on Wed 11 August.
  • ABB FAT postponed due to fire in the factory, early warning submitted to Melbourne Water, update officially submitted through ASITE.
  • CE 11, CE12 and CE13 submitted.

ETP Recuperative Thickener IPPN
Approved ~ Q05772
  • AMES – commenced preparation for North SDP pipework tie-in scheduled Oct 2021.
  • Chadoak – installation of fire water in RT.
  • Tankweld/AMES  – completed mechanical installation in wet polymer area. Continue mechanical fitout in RT building. Continue pipework decommissioning and preparation works for gallery pipework. 
  • ADX Electrical – continue installation of cable management infrastructure in LV building, RT building and Polymer building.
  • CLQA – mobilized and works in progress.
  • Trivantage – switchboards installed on site.
  • Electro80 – continue PLC programming and preparation for 62HC breaker commissioning.
  • SFPJV – HV infrastructure installation in progress.
ETP Waste Activated Sludge ~ Q05102
  • Scaffold access installed in tanks 8, 11 and 12.
  • Preparation of mobilisation of Mattioli for concrete repair works.
  • Procurement of major equipment continues (electrical installation, mechanical installation, valves, instruments, scraper system).
  • IFC design development in progress.

WTP Electrical Reliability Additional Works ~ F10133
  • 55E Lagoon control panel installation works have started.
  • The construction and commissioning plan for 55E Lagoon works has been finalised.
  • SFP JV received approval for CE13 – WTP25W SCADA Modification Works.
  • Procurement – waiting for delivery of 3 x RMUs from Eaton, 3 x Control Boxes from Electro80 and LLIs from Schneider. The contracts with ABB and Schneider for the supply and installation of LLI have been finalised.
WTP 25W Lagoon Pond 1 HV and LV Renewals ~ F10461
  • Financial set up in progress.
  • Design kick-off.