Bid Status
Project | Job | Value | Status |
---|---|---|---|
Yan Yean Pump Station | Q05322 | $20M | Working |
Winneke Treatment Plant – UV Disinfection System | Q03309 | $40M | Working |
Yan Yean Bald Hill Pipeline | Q05333 | $30M | Working |
M22 and M46 Main Replacement | Q02539 | $37M | Working |
Winneke Fluoride Plant Upgrade | Y10207 | $7M | Lost |
Gardiners Creek Main Sewer Rehabilitation | Y10248 | $12.3M | Submitted |
Maribyrnong Main Sewer Augmentation | P31258 | $55.2M | Submitted |
HV Infrastructure Improvements | Y10260 | $750k | Submitted |
Project Delivery Update
Hawthorn Main Sewer Rehabilitation~ P33546 |
- SFPJV have completed all tasks and actions for Stage 2.
- Awaiting Melbourne Water to issue formal certificate.
Holden Reservoir M486 Inlet Pipeline SP1 & SP2~ Q03295 |
- Final restorations completed awaiting a confirmation from Melbourne Water that the LFI earthing will be approved.
REFCL Tranche 2 Electrical Compliance B Thompson Hydro ~ Y10219 |
- Stage 2 completion date achieved on 16 July 2021.
Yan Yean WTP Upgrade~ Q04385 |
- Electrical:
- Decommissioning DFs, MCCs and cables.
- Civil:
- Backwash Tanks. Central Channel Connection concrete pour
- FSA Building. Precast concrete wall panels installation
- Delay Tank. Formwork for Mech Screen wall.
- Underground pipework:
- Commence concrete reinstatement and pipe installation on DN375 filter to waste line on east side of DFs
- Backfill DN375 filter to waste line, Plant return line and Relift to GAC inlet on west side of DFs
- Raw water inlet line. Scour installation and removal of redundant line
- Mechanical:
- Continue removal of chemical dosing lines
- Removal of lime from lime silo
- TDU:
- Process commissioning – CO2 PLC interlock fault correction works
Lillydale Lake Wetland Rectification Approved ~ Y10192 |
- Topsoil is being placed is at 60% complete.
- Traction on the approval of some of the CE’s is in place.
- Melbourne Water working on getting a quantum approved in September.
Winneke Main Sub Station Switchboard Replacement ~ D10103 |
- All design deliverables have been finalised and the long lead time materials have been procured.
- 11kV SWBD Bus A outage works have been completed. The old Bus A has been decommissioned and removed from the site.
- The DC Battery System installation works have been completed.
- New 11kV SWBD Bus A installation works have started. The next plant wide outage will be at the end of August 202.
- All Change Events are approved except CE01 – Solar works. The revised CE was submitted to Melbourne Water and waiting for their approval.
Youell Street Sewer Renewals ~ Q07136 |
- Stage 1 achieved and all omissions and outstanding items of work completed.
- A final technical memo to be produced detailing compliance of the liner.
- Currently working on As- built drawings.
ETP HV-62A Switchboard & VH-LV Renewals ~ Y10307 (Q05103) |
Civil Infrastructure Group (CIG) have completed:
- Pour concrete base of cable culvert.
- Excavation for exiting conduits next to new building.
- Investigation – existing HV cable routes in progress.
- Design cost for Unit Sub new location approved by Melbourne Water.
- Meeting with ETP OPS regarding the cutover sequence completed.
- Procurement:
- NER delivered.
- Change Events approval:
- All CEs but CE03 Unit subs approved in principle – to be combined in one TCE adjustment.
ETP Recuperative Thickener IPPN Approved ~ Q05772 |
- Delfab – completed installation of cable/pipe supports around RT and Polymer building. Completed installation of mezzanine structure.
- AMES – completed installation of thrust block and backfilled pipeline.
- Chadoak – hydrotest successfully completed for all pipework and installation completed. Planning works for 1W tie-in in progress.
- Comcraft – complete fit out of LV building and installation of doors.
- Tankweld/AMES – 100% complete for SDP pipework installation in gallery. Preparing for hydrotest. Installation team for RT site continue installation of Sludge Drying Pan Pump Station, Booster Pump Station and RDTs.
- ADX Electrical – continue installation of cable management infrastructure in LV building, RT building and Polymer building. Planning works for switchboard installation in LV building.
- CLQA – offsite fabrication of OCF vessels 95% complete.
- Trivantage – switchboard FAT completed 26 July 2021.
- Electro80 – control panels delivered to site.
ETP Waste Activated Sludge ~ Q05102 |
- Hydrotesting of Tank 8 completed.
- Hydrotest of Tank 11 & 12 on the way.
- Procurement of major equipment continues (switchboards, instruments, scraper system, mechanical installation).
- 90% design review completed 29 July 2021.
WTP Electrical Reliability Additional Works ~ F10133 |
- 55E Lagoon control panel installation works have started.
- The construction and commissioning plan for 55E Lagoon works has been finalised.
- SFPJV received approval for CE13 – WTP25W SCADA Modification Works.
- Procurement – waiting for delivery of 3 x RMUs from Eaton, 3 x Control Boxes from Electro80 and LLIs from Schneider. The contracts with ABB and Schneider for the supply and installation of LLI have been finalised.
WTP 25W Lagoon Pond 1 HV and LV Renewals ~ F10461 |
- APN was received.
- Project setup is currently in progress.