Bid Status
Project | Job | Value | Status |
---|---|---|---|
Mt Evelyn WTP (aka Silvan DRP) | F10270 | $12M+ | Working |
Hoppers Crossing Power Reliability System Upgrade | Q03109 | $3M | Working |
Project Delivery Update
Holden Reservoir M486 Inlet Pipeline SP1 & SP2~ Q03295 |
- Stage 1 certificate received 8 April.
Yan Yean WTP Upgrade~ Q04385 |
- FRP of delay tank walls and penetrations in preparation for concrete pour on 5 August.
- FRP for FSA waste tank infrastructure and modifications of risers to TWPS above ground pipework.
- Mechanical installation continue in TWPS, Hypo Building and Backwash PS.
- Electrical installation continue with chemical switch-room fit-out and MCC switch-room.
- Continue painting of wastewater equalisation Tank.
- Commence demolition of existing hypo building in preparation for relocation of site shed infrastructure.
Yan Yean Pump Station ~ Q05322 |
- Day 1 readiness in progress.
- Demolition of existing hypo building and relocation of crib facilities.
- Review of revised suction pipeline alignment inside YYWTP.
- Technical memo for pump selection completed. Procurement of pumps in progress.
- RFQs obtained for electrical equipment. Assessment in progress.
Yan Yean Bald Hill Pipeline ~ Q05333 |
- The project has onboarded a new junior project controller.
- IFC drawings progressing and the corrosion control design and construct package has been returned to review with Melbourne Water.
- Commencing the development of welding procedures and QA documentation.
Winneke Main Sub Station Switchboard Replacement ~ D10103 |
- RMU package – RMU141 and RMU143 are delivered and positioned. Cable termination in progress.
- PLC package – delivered to site
- HV Cables – delivered to site.
- FO Cables – delivered to site.
- Civil works – 90% completed.
- Electrical installation works are in progress.
ETP HV-62A Switchboard & VH-LV Renewals ~ Y10307 (Q05103) |
- PFC area hand over.
- Internal doors installed; fire rated enclose under construction.
- T1 door way frame installedT1 vault, redundant fire suppression system pipe work removed from ceiling.
- Continued installing cables to remote ends of plant.
- Continued HV cable termination on new #2 transformer.
- Started decommissioning works on the OPS emergency generator.
- Continued testing in 62HA.
- Completed fibre splicing in 62HA and 62H.
- Completed hole coring in 62H.
- Continued with door modifications between 62H and 62HB.
- PSD engaged for PFC controller logic.
ETP Recuperative Thickener ~ Q05772 |
- Continue process commissioning.
- Pan pre-thickening change event submitted 3 August.
ETP Waste Activated Sludge ~ Q05102 |
- Completion of DAF Tanks 8,11 12 on 4 August, with removal of scissor lifts.
- Flange management in gallery pipework.
- Terminations of equipment and instruments in progress.
WTP Electrical Reliability Additional Works ~ F10133 |
- Design
- IFC – design completed.
- CE – the revised protection study completed.
- Schneider LLI works scheduled for January 2022 finished. The last set of LLIs initially scheduled for April 2022 postponed until protection study is completed.
- ABB LLI works completed. 25W Blower Building SCADA works are in progress – 90% completed. The remaining works can’t be completed until a separate CE is approved by Melbourne Water.
- A CE has been submitted to Melbourne Water to claim additional cost and EOT resulted from protection setting upgrade works. The revised PC1 date is in November 2022
- An early warning letter has been submitted regarding the protection study. The planned activities can’t be completed until the protection study is approved.
WTP 25W Lagoon Pond 1 HV and LV Renewals ~ F10461 |
- Design
- Civil Design – IFC drawings updated based on the construction crew comments.
- MLCs – 100% design submitted for review.
- Control Philosophy – Melbourne Water comments received, IFC design in progress.
- Procurement
- RMU – ordered, delivery expected mid October.
- RMU Control Panel – executing contract with Electro80.
- HV Kiosks – work on 30% design progressing.
- FO Cable – delivered to Downer Dandenong Depot.
- HV Cable – ordered, delivery expected mid July.
- LV Cables – ordered, delivery expected mid August.
- Construction
- Civil works progressing (construction zone 6, 7 and 8). Zone 1-5 works completed.
Gardiners Creek Sewer Rehabilitation ~ Y10248 |
- Completed a big week with a further 3 liners installed utilising a crew from ACI in Sydney
- Substation liner now installed, and Monash being installed on weekend of the 6 August.
- The project now has 2 CIPP liners to install and 7 spiral liners.
Maribyrnong Main Sewer Augmentation ~ P31258 |
- Fifth blast completed and works commencing on excavation of the next lowering of the shaft.
- Shaft now down 10.1m and challenge to maximise blast depth whilst trying to maintain the vibration levels withing the allowable limits. Six working week now in place.
- Bridge design progressing to allow first pricing of ancillary concrete retaining wall works, but CHMP delays now moving to critical path.
Interlocking Safety Upgrades for HV Water Sites ~ Y10260 |
- Contract executed, and locked in dates with Schneider Electric to perform interlock works.
- Completed Interlocking works at Silvan Mini Hydro and Thomson Hydro. MW Operators were trained on the new key interlocking changes.
- Schneider Electric advised the Key Exchange Boxes are not ready for Cardinia Pumping station, works have been rescheduled to start of September.
Hoppers Crossing Pump Station 66kV ~ F10428 |
- Survey files by Taylors have been submitted.
- Geotech report by Cardno has been submitted.
- 30% Design Package has been developed and is currently under internal review.
- Upcoming Activities
- 30% Design Package activities: internal review process.
- Submission to Melbourne Water for review.