Bid Status
Project | Job | Value | Status |
---|---|---|---|
Mt Evelyn WTP (aka Silvan DRP) | F10270 | $12M+ | Working |
Hoppers Crossing Power Reliability System Upgrade | Q03109 | $3M | Working |
Project Delivery Update
Holden Reservoir M486 Inlet Pipeline SP1 & SP2~ Q03295 |
- Stage 1 certificate received 8 April.
Yan Yean WTP Upgrade~ Q04385 |
- Installation of conduits completed. Install replacement valves in chemical building.
- Mechanical installation continues in lime building, Groundwater Transfer PS and Hypo building.
- Electrical installation continues with chemical switch room fit-out and MCC switch room.
- Continue sand blasting and painting of wastewater equalisation tank.
- FRP wall installed and planning of hydrotest in progress.
- FSA dosing and transfer skid arrived on site.
Yan Yean Pump Station ~ Q05322 |
- Day 1 readiness in progress.
- Commenced service proving and geotechnical investigations.
Winneke Main Sub Station Switchboard Replacement ~ D10103 |
- RMU141 Delivered to site. ABB informed that RMU143 is scheduled to be delivered to the site on 7 July.
- In progress of Civil works and electrical construction works at Winneke Mini Hydro and HV Substation sites.
- Mini Hydro Site – all the HV cables trifurcated. The fencing works and civil footing works completed.
- Main Sub Station – RMU 141 installation works started – eeceived all the IFC design deliverables from PSD.
ETP HV-62A Switchboard & VH-LV Renewals ~ Y10307 (Q05103) |
- Completed installation of 22kV cable hauling between 84EH and New #2 Transformer.
- Completed removal of OSS#1 TX.
- Completed foundation concrete pour for OPS generator.
- Started modification works in OSS#1 TX Vault.
- Continued installing control cables to remote ends of the plant.
- Continued works on control desk.
- Started installation of fibre cable in power station.
ETP Recuperative Thickener ~ Q05772 |
- Multi-project merge completed 30 June with no major issues. Minor issue with additional PCS licenses required. Currently being procured for installation.
- Commissioning in progress.
- Demobilization of site sheds completed.
ETP Waste Activated Sludge ~ Q05102 |
- Gallery:
- CAS panel piping – unfiltered and filtered completed this week.
- Pipe support for 8 and 11 WAS/ASW header.
- 65mm Saturator pipe and vent installation.
- Installation of drain lines from saturator.
- DAF 8, 11 & 12
- TWAS pump piping as much as possible – remainder to complete after sludge trough installation.
- Sludge trough panels delivery and loading into tanks.
- Tensioning system for DAF tanks.
- Cabling to RIO panel at DAF tank 8.
- Cable tray system installation – finalising.
WTP Electrical Reliability Additional Works ~ F10133 |
- The Protection study has been submitted as part of CE. Received a few comments back from PowerCor. Resubmitting the report by the end of week.
- All the electrical fitting works completed apart from POC 2 works, which. is currently on hold until we receive the approval for protection study. An early warning letter has been submitted to Melbourne Water.
- The reactor demolition works complete.
- Blower Building LLI SCADA works in progress – 60% completed.
WTP 25W Lagoon Pond 1 HV and LV Renewals ~ F10461 |
- Civil works progressing (construction zone 5 & 6). Zone 1-4 works completed.
- MLCs – 80% design. Melbourne Water comments received, being actioned.
- RMU – comments on secondary drawings sent to Eaton. Delivery expected mid-October.
- Fibre Cable – delivered, at Downer Dandenong Depot.
- HV Kiosks – work on 30% design has started.
- HV Cable – delivery expected mid-July.
- LV Cables – RFQ process progressing. Nexans shortlisted.
- RMU Control Panel – executing contract with Electro80.
- Control Philosophy – Melbrourne Water comments received, being actioned.
Gardiners Creek Sewer Rehabilitation ~ Y10248 |
- Some delays onsite in the relining of CIPP due to resource issues with parent company. Resources to be supplemented with resources from ACI Sydney.
- Last of the Spiral and CIPP materials arrived in Melbourne.
- The bypass systems for the CIPP works are all now installed and commissioned.
Maribyrnong Main Sewer Augmentation ~ P31258 |
- First blast completed and works commencing on excavation of the next lowering of the shaft
- Flow management plans being developed for measurement and inspection of the North Western main.
- Bridge design progressing to allow first pricing of ancillary concrete retaining wall works.
Interlocking Safety Upgrades for HV Water Sites ~ Y10260 |
- SE completed site visit to Cardinia to confirm key exchange boxes arrangement.
- Upcoming Activities:
- Completion of Project Management Documents.
- Execution of contract with SE for the installation works.
- Schneider Electric has confirmed the interlock kits have arrived.
- Preparation of outage permits for Silvan, Thomson, Cardinia and Preston.
- Prepare site works from 8 July.
Hoppers Crossing Pump Station 66kV ~ F10428 |
- Issue for Tender documents for long lead items have been issued to Melbourne Water for review 17 June, responses will be submitted this week on 5 July.
- Survey investigations (including NDD) by Cardno are complete. Report submission by 28 July.
- Geotech investigations (including NDD) by Taylors are complete. Report submission by 28 July.
- Earth grid testing by PSD Energy is underway. Expected site completion 6 July.