Bid Status

ProjectJobValueStatus
ETP Power Management ChangesH11894$482KWon
Mordialloc Main Sewer RehabY10341$12.4MSubmitted
Refurb of Werribee Hanger 1Y05707$23MSubmitted
ETP Digester UpgradesY10286$70MSubmitted
Thomson Dam Capacitor UpgradeY10364$3.5MSubmitted
Tarago Fluoride Plant UpgradeY10209$10MSubmitted
WTS Emergency Management PlanQ05622$250kSubmitted (July)
North Heatherton Wetland RenewalF10465$10MSubmitted (July)
Waverley Rd Retarding Basin SpillwayF10476$5MWorking

Project Delivery Update

North Yarra Main Relining Upper Section ~ Y10234
  • All relining completed and post lining laser scanning completed
  • MH reinstatement completed
  • Yarraman Riders Association Paddocks demobilised and reinstated
  • 7 of 15 junction seal completed (3No lines remain)

M76 Water Main Renewal ~ Q02707
  • Asbestos removal and removal of existing concrete foundations in Fleet St completed.
  • Completed St Alban St connection works after delays with MWC shutdown of main of approx 4 weeks.
  • House demolition in Charles St commenced.

Essex Main Drain Renewal ~ Y10314
  • Stage 1 Completion documents submitted.
  • Early Works for Erica St change event completed. Awaiting Change Event approval.

Maribyrnong Main Sewer Augmentation ~ P31258
  • Launch Shaft:
    • Tunnel stripping and demobilisation continues.
  • Adit:
    • Temp works design in work – Noma
    • Jacking shield design and fabrication in work
    • Exploratory bores x 2 complete – 1 x to map BGF / Gellibrand Marl interface, & 1 x to prove dewatering spear methodology.
  • Riverside:
    • Direction Notice #2: Complete
    • Direction Notice #3: Issued 3rd June 2024 – Removal of Riverside scope; response provided on the 26th June 2024
    • Direction Notice #4: Issued 21st  June 2024 – Geotech test & TBM results to be provided to MW, response provided 2nd July 2024
Yan Yean WTP Upgrade ~ Q04385
  • Feed commenced to TWST/water network 18 June
  • Plant is operating at 23ML/d
  • Investigations ongoing for high fluoride excursion
Yan Yean Pump Station ~ Q05322
  • Stage 1 achieved 19 June
  • Closeout of Stage 2 items in progress
  • CH0 final connection welding completed
Yan Yean Bald Hill Pipeline ~ Q05333
  • Delcon works delayed due to rubber rings not being available due to issues with steel mains.
  • Tunnel at Merri Creek has progressed 130m.
  • Rail shafts nearing completion.
  • Pipeline tie-ins completed at chainage 0 and chainage 13520
Hoppers Crossing Pump Station 66kV ~ F10428
  • CCTV Package has been reviewed by Melbourne Water with no further comments.
  • CEMP has been reviewed by Melbourne Water, currently being actioned by SFP.
  • 30% design package for Q03109 Power Reliability has been issued for review. Comments from Melbourne Water have been received and addressed. Issued the comments register back to Melbourne Water for response.
  • Safety-in-Design and CHAIR1 workshop comments sitting with Melbourne Water for response.
  • Accenture engaged for SCADA works, contracts established.
  • 30% design controls scope clarifications currently sitting with Melbourne Water.
 WTP 55 East HV/LV (CE to 25W)
  • Change Event for new site facility and laydown area submitted.
  • MLC spec has been updated incorporating Melbourne Water comments. It has been reissued to Melbourne Water on 27/05 for final approval.
  • 50% Civil design drawings issued for review on 21 May.
  • Work on MLC contract progressing (Trivantage).
 WTP 66kV
  • Working on finalisation of the SOW document this week
  • Melbourne Water intends to first issue the project for Design only.
Thompson Hydro Capacitor Bank – Y10364
  • The main project tender submitted – Approval delayed until end of July.
ETP Waste Activated Sludge ~ Q05102
  • PoPT ITP submitted and addressing Melbourne Water comments.
  • Final Proof of Performance to commence July 24.
ETP Recuperative Thickener ~ Q05772
  • Closing out Stage 2 items.
ETP Areas 15 to 26 ~ F10730
  • Both kiosk specs have been received
  • Tender packages have been sent out for both kiosks
  • Quotes have been received from suppliers on 21/06/24
  • Quotes currently being evaluated.
  • HV Cables IFTs have been received
  • Quotes have been received and currently under review
  • Access to redeye, provided to designers.
  • 30% design deliverables, in progress.
  • Structural deliverables received, has been reviewed. Comments sitting with the designers.
  • Secondary electrical design has been started.
  • Electrical primary drawings currently under internal review.