Bid Status
Project | Job | Value | Status |
---|---|---|---|
ETP Power Management Changes | H11894 | $482K | Won |
Mordialloc Main Sewer Rehab | Y10341 | $12.4M | Submitted |
Refurb of Werribee Hanger 1 | Y05707 | $23M | Submitted |
ETP Digester Upgrades | Y10286 | $70M | Submitted |
Thomson Dam Capacitor Upgrade | Y10364 | $3.5M | Submitted |
Tarago Fluoride Plant Upgrade | Y10209 | $10M | Submitted |
WTS Emergency Management Plan | Q05622 | $250k | Submitted (July) |
North Heatherton Wetland Renewal | F10465 | $10M | Submitted (July) |
Waverley Rd Retarding Basin Spillway | F10476 | $5M | Working |
Project Delivery Update
North Yarra Main Relining Upper Section ~ Y10234 |
- All relining completed and post lining laser scanning completed
- MH reinstatement completed
- Yarraman Riders Association Paddocks demobilised and reinstated
- 7 of 15 junction seal completed (3No lines remain)
M76 Water Main Renewal ~ Q02707 |
- Asbestos removal and removal of existing concrete foundations in Fleet St completed.
- Completed St Alban St connection works after delays with MWC shutdown of main of approx 4 weeks.
- House demolition in Charles St commenced.
Essex Main Drain Renewal ~ Y10314 |
- Stage 1 Completion documents submitted.
- Early Works for Erica St change event completed. Awaiting Change Event approval.
Maribyrnong Main Sewer Augmentation ~ P31258 |
- Launch Shaft:
- Tunnel stripping and demobilisation continues.
- Adit:
- Temp works design in work – Noma
- Jacking shield design and fabrication in work
- Exploratory bores x 2 complete – 1 x to map BGF / Gellibrand Marl interface, & 1 x to prove dewatering spear methodology.
- Riverside:
- Direction Notice #2: Complete
- Direction Notice #3: Issued 3rd June 2024 – Removal of Riverside scope; response provided on the 26th June 2024
- Direction Notice #4: Issued 21st June 2024 – Geotech test & TBM results to be provided to MW, response provided 2nd July 2024
Yan Yean WTP Upgrade ~ Q04385 |
- Feed commenced to TWST/water network 18 June
- Plant is operating at 23ML/d
- Investigations ongoing for high fluoride excursion
Yan Yean Pump Station ~ Q05322 |
- Stage 1 achieved 19 June
- Closeout of Stage 2 items in progress
- CH0 final connection welding completed
Yan Yean Bald Hill Pipeline ~ Q05333 |
- Delcon works delayed due to rubber rings not being available due to issues with steel mains.
- Tunnel at Merri Creek has progressed 130m.
- Rail shafts nearing completion.
- Pipeline tie-ins completed at chainage 0 and chainage 13520
Hoppers Crossing Pump Station 66kV ~ F10428 |
- CCTV Package has been reviewed by Melbourne Water with no further comments.
- CEMP has been reviewed by Melbourne Water, currently being actioned by SFP.
- 30% design package for Q03109 Power Reliability has been issued for review. Comments from Melbourne Water have been received and addressed. Issued the comments register back to Melbourne Water for response.
- Safety-in-Design and CHAIR1 workshop comments sitting with Melbourne Water for response.
- Accenture engaged for SCADA works, contracts established.
- 30% design controls scope clarifications currently sitting with Melbourne Water.
WTP 55 East HV/LV (CE to 25W) |
- Change Event for new site facility and laydown area submitted.
- MLC spec has been updated incorporating Melbourne Water comments. It has been reissued to Melbourne Water on 27/05 for final approval.
- 50% Civil design drawings issued for review on 21 May.
- Work on MLC contract progressing (Trivantage).
WTP 66kV |
- Working on finalisation of the SOW document this week
- Melbourne Water intends to first issue the project for Design only.
Thompson Hydro Capacitor Bank – Y10364 |
- The main project tender submitted – Approval delayed until end of July.
ETP Waste Activated Sludge ~ Q05102 |
- PoPT ITP submitted and addressing Melbourne Water comments.
- Final Proof of Performance to commence July 24.
ETP Recuperative Thickener ~ Q05772 |
- Closing out Stage 2 items.
ETP Areas 15 to 26 ~ F10730 |
- Both kiosk specs have been received
- Tender packages have been sent out for both kiosks
- Quotes have been received from suppliers on 21/06/24
- Quotes currently being evaluated.
- HV Cables IFTs have been received
- Quotes have been received and currently under review
- Access to redeye, provided to designers.
- 30% design deliverables, in progress.
- Structural deliverables received, has been reviewed. Comments sitting with the designers.
- Secondary electrical design has been started.
- Electrical primary drawings currently under internal review.