Bid Status

ProjectJobValueStatus
ETP Areas 15-26 UpgradesF10730$22.4MWon
WTP 55E Pond 1 MLC RenewalF10427$14.9MWon
WTP HV Power & Energy Resilience ECIQ03817$472KWon
ETP Power Management ChangesH11894$482KSubmitted
Quarry Hill TankF10365$18.8MSubmitted
Mordialloc Main Sewer RehabY10341$12.4MSubmitted
Refurb of Werribee Hanger 1Y05707$23MWorking
ETP Digester UpgradesY10286$70MWorking
Thomson Dam Capacitor UpgradeY10364$3.5MWorking
Tarago Fluoride Plant UpgradeY10209$10MWorking

Project Delivery Update

North Yarra Main Relining Upper Section ~ Y10234
  • All MH modifications pre-lining completed.
  • Hazardous tree removed from work area.
  • Bypass demobilised.
  • Lining To date:
    • 5No lines 490m of 450mmØ sewer
    • 7No line 892m of 600mmØ sewer

Tarago Fluoride Plant Upgrade ECI ~ Y10209
  • ECI completed.
M76 Water Main Renewal ~ Q02707
  • Pipelaying ongoing in High Street Rd to chainage 753m of 1160m.
  • Lawrence Street crossing completed.

Essex Main Drain Renewal ~ Y10314
  • Garden St works completed including reinstatement.
  • Early Works for Errica St change event completed.

Maribyrnong Main Sewer Augmentation ~ P31258
  • Launch Shaft
    • 680m complete (58m for March).
    • Head pressures remain high throughout the month.
    • Pipe damage at IJ4 required repair.
    • Slurry Pump 2.3 and 2.2 failed and required replacement.
    • Temp works design and procurement for Adit construction underway
  • Riverside:
    • Direction Notice #1 – Site has been demobilised.
    • Direction Notice #2: Updated Budget pricing incorporating Geotech.
    • information and Temp works shaft design in work ongoing.
    • HEC-RAS flood calibration to be updated and resubmitted – ongoing.
Yan Yean WTP Upgrade~ Q04385
  • Completed temporary PLC cut-over.
  • PoPT to commence April 2024.
Yan Yean Pump Station ~ Q05322
  • External suction pipeline installation works along Recreation Road ongoing.
  • Continue secondary cable installation.
  • Final torquing completed for mechanical works.
  • Landscaping and roadworks ongoing.
Yan Yean Bald Hill Pipeline ~ Q05333
  • Winslow completed SP3 up to Rail.
  • Pipe install at 89% complete.
  • Shaft construction at Merri creek underway:
    • Receival shaft down 4m
    • Launch Shaft down 5.5m
  • TBM equipment tunnelling team mobilising.
Hoppers Crossing Pump Station 66kV ~ F10428
  • Design – Progressing to next milestone (IFC).
  • CE03 – Escalation costs on Main Project delay due to Q03109. Approximately $536k. Submitted to Melbourne Water on 8 December.
WTP 25W Lagoon Pond 1 HV and LV Renewals ~ F10461
  • All kiosks commissioned and energised.
  • Stage 1  –  28 March 2024. Pending Melbourne Water signature.
ETP HV-62A Switchboard & VH-LV Renewals ~ Y10307 (Q05103)
  • Readiness Day 1 documentation stage.
ETP Waste Activated Sludge ~ Q05102
  • Report to be provided for TWAS pump performance.
  • Final Proof of Performance to commence in April.
ETP Recuperative Thickener ~ Q05772
  • Closing out Stage 2 items.