Bid Status
Project | Job | Value | Status |
---|---|---|---|
ETP Areas 15-26 Upgrades | F10730 | $22.4M | Won |
WTP 55E Pond 1 MLC Renewal | F10427 | $14.9M | Won |
WTP HV Power & Energy Resilience ECI | Q03817 | $472K | Won |
ETP Power Management Changes | H11894 | $482K | Submitted |
Quarry Hill Tank | F10365 | $18.8M | Submitted |
Mordialloc Main Sewer Rehab | Y10341 | $12.4M | Submitted |
Refurb of Werribee Hanger 1 | Y05707 | $23M | Working |
ETP Digester Upgrades | Y10286 | $70M | Working |
Thomson Dam Capacitor Upgrade | Y10364 | $3.5M | Working |
Tarago Fluoride Plant Upgrade | Y10209 | $10M | Working |
Project Delivery Update
North Yarra Main Relining Upper Section ~ Y10234 |
- All MH modifications pre-lining completed.
- Hazardous tree removed from work area.
- Bypass demobilised.
- Lining To date:
- 5No lines 490m of 450mmØ sewer
- 7No line 892m of 600mmØ sewer
Tarago Fluoride Plant Upgrade ECI ~ Y10209 |
- ECI completed.
M76 Water Main Renewal ~ Q02707 |
- Pipelaying ongoing in High Street Rd to chainage 753m of 1160m.
- Lawrence Street crossing completed.
Essex Main Drain Renewal ~ Y10314 |
- Garden St works completed including reinstatement.
- Early Works for Errica St change event completed.
Maribyrnong Main Sewer Augmentation ~ P31258 |
- Launch Shaft
- 680m complete (58m for March).
- Head pressures remain high throughout the month.
- Pipe damage at IJ4 required repair.
- Slurry Pump 2.3 and 2.2 failed and required replacement.
- Temp works design and procurement for Adit construction underway
- Riverside:
- Direction Notice #1 – Site has been demobilised.
- Direction Notice #2: Updated Budget pricing incorporating Geotech.
- information and Temp works shaft design in work ongoing.
- HEC-RAS flood calibration to be updated and resubmitted – ongoing.
Yan Yean WTP Upgrade~ Q04385 |
- Completed temporary PLC cut-over.
- PoPT to commence April 2024.
Yan Yean Pump Station ~ Q05322 |
- External suction pipeline installation works along Recreation Road ongoing.
- Continue secondary cable installation.
- Final torquing completed for mechanical works.
- Landscaping and roadworks ongoing.
Yan Yean Bald Hill Pipeline ~ Q05333 |
- Winslow completed SP3 up to Rail.
- Pipe install at 89% complete.
- Shaft construction at Merri creek underway:
- Receival shaft down 4m
- Launch Shaft down 5.5m
- TBM equipment tunnelling team mobilising.
Hoppers Crossing Pump Station 66kV ~ F10428 |
- Design – Progressing to next milestone (IFC).
- CE03 – Escalation costs on Main Project delay due to Q03109. Approximately $536k. Submitted to Melbourne Water on 8 December.
WTP 25W Lagoon Pond 1 HV and LV Renewals ~ F10461 |
- All kiosks commissioned and energised.
- Stage 1 – 28 March 2024. Pending Melbourne Water signature.
ETP HV-62A Switchboard & VH-LV Renewals ~ Y10307 (Q05103) |
- Readiness Day 1 documentation stage.
ETP Waste Activated Sludge ~ Q05102 |
- Report to be provided for TWAS pump performance.
- Final Proof of Performance to commence in April.
ETP Recuperative Thickener ~ Q05772 |
- Closing out Stage 2 items.