ProjectJobValueStatus
North Yarra Main Relining Upper SectionY10234$12MWorking
Hoppers Crossing Power Reliability System UpgradeQ03109$3MWon


Project Delivery Update

M76 Water Main Renewal ~ Q02707
  • Still awaiting APN.
  • Purchase order issued for Early Works.
  • Notifications for early works investigations (service location and proving) has been issued to stakeholders.

Essex Main Drain Renewal ~ Y10314
  • Draft APN issued for review and comment.
  • Engagement of new SPE for project commenced.
  • Day 1 readiness procedures and tasks have commenced.

Maribyrnong Main Sewer Augmentation ~ P31258
  • Launch Shaft depth: 32.2m.
    • Construction has paused.
    • Works undertaken to stabilise the Brighton Group geotechnical layer have been unsuccessful (Grout injection, Spile Bar installation) primarily due to the non-cohesive nature of the sands and the residual ground water observed within the Brighton Group formation.
  • Riverside:
    • Churchill Drain crossing continuing.
    • Vegetation stripping continuing.
    • Receival shaft excavation progressing depth: 4.8m.
    • Bridge package RFA: Delfab.
    • Piling RFQ issued, poor response, further work needed.

Yan Yean WTP Upgrade~ Q04385
  • Continue mechanical and electrical fit-out.
  • Commissioning Manager commenced on site and working through comments on Commissioning and Energisation Plan.
Yan Yean Pump Station ~ Q05322
  • Relocation of services completed.
  • Bulk earthworks in progress.
Yan Yean Bald Hill Pipeline ~ Q05333
  • Still waiting for final environmental approvals from Whittlesea Council, delays are associated with incorporating the pump station permit conditions into the pipeline planning permit. Melbourne Water forgot to request approval for vegetation clearing at pump station site.
  • CHMP West approved and works can commence in the west paddock sections.
  • Working with Winslow and subcontractors to re-validate pricing/subcontracts.
  • Audit completed some minor actions and administrative actions to close out
Hoppers Crossing Pump Station 66kV ~ F10428
  • Detailed design for the 80% design package is has been issued to Melbourne Water for review.
  • Q03109 Power Reliability – early works of this scope is underway. Load study and HV Circuit Breaker specification has been issued to Melbourne Water. Meeting was held between Melbourne Water/SFP to discuss concept design. Melbourne Water have determined the options provided were not acceptable – a new location is to be reviewed by SFP.
  • SFP attended site to inspect new nominated location. Location will be reviewed and further information will be requested in order to proceed.
  • Early procurement of Siemens CB has been approved for the pending Power Reliability variation works. Currently in negotiations with Siemens.
WTP 25W Lagoon Pond 1 HV and LV Renewals ~ F10461
  • Design
    • LV Control Narrative – Updated document issued for MW review.
    • HV Control Narrative – Being updated based on CHAZOP.
    • LV Protection and Arc Flash Report – Updated document issued for MW review.
    • HV Protection Report – MW comments received, being actioned.
    • RMU Control Panel – IFC drawings being finalised.
  • Procurement
    • MLCs – All MLCs have been delivered.
    • All HV, LV and FO cables have been delivered.
  • Construction
    • Install FO cable from 48ZDA to NE corner of 25W Pond 1.
    • Install ladder lids on aerator stands along South Rd.
    • Roping of existing FO conduits along North Rd.
    • Delivery and installation of 48ZAB and 48ZAA MLCs.
  • Testing and Commissioning
    • Pre-commissioning and testing of 48ZDB and 48ZDA MLCs.
ETP HV-62A Switchboard & VH-LV Renewals ~ Y10307 (Q05103)
  • Completed removal of OSS T1 and T2 heat exchangers including associated pipework.
  • Completed cut-over works of 6.6kV 33H feeder from 62H to new 62HA.
  • Continued civil works for 33H cutover including cable pit modifications.
  • Completed cable installation on second 54M feeder. 1 cable 350m.
  • Started cut-over works of 6.6kV  71M feeder from 62H to new 62HA.
ETP Waste Activated Sludge ~ Q05102
  • DAF 8,11 and 12 Commissioning Report submitted to Melbourne Water. Working through Melbourne Water comments.
  • DAF 1 fitout completed. Beach plate modification in progress.
  • DAF 7 fitout ongoing.
ETP Recuperative Thickener ~ Q05772
  • Second 14 day PoP test to commenced 29 March.
Gardiners Creek Sewer Rehabilitation ~ Y10248
  • Stage 1 being requested.
  • Final agreement on payment of works to complete the project has been finalised.

Holden Reservoir M486 Inlet Pipeline SP1 & SP2~ Q03295
  • Stage 1 certificate received 8 April, 2022.
  • Awaiting Melbourne Water to provide data for Stage 2 and 3.