Bid Status
Project | Job | Value | Status |
---|---|---|---|
Mt Evelyn WTP (aka Silvan DRP) | F10270 | $12M+ | Working |
Hoppers Crossing Power Reliability System Upgrade | Q03109 | $3M | Working |
Project Delivery Update
Holden Reservoir M486 Inlet Pipeline SP1 & SP2~ Q03295 |
- Stage 1 certificate received 8 April.
Yan Yean WTP Upgrade~ Q04385 |
- Civil – backwash slab completed. Continue FRP of pipe penetrations. Concrete lining in cast in backwash header completed and recoating works continue. Cleaning of centre channel completed.
- Mechanical – install pipework in lime building. Installation of coag/poly aid skids completed. Removal of backwash header and equipment for refurbishment. Commence backwash pump station installation.
- Electrical – Main swtichroom major infrastructure installed. Continue fit out and rough in at alum/coag/lime building. Commence installation of conduits.
- Underground piping – completed install of TWT inlet and commissioning bypass pipeline. Commence conduit installation.
- HVAC mechanical installation completed in FSA building.
- Commence installation of FRP dividing wall in filter channel.
Yan Yean Pump Station ~ Q05322 |
- 30% design submitted to MW in preparation for 30% design workshop.
- Day 1 readiness in progress.
- Project Engineer (Jack Dodds) onboarding in progress and scheduled to start in June.
Winneke Main Sub Station Switchboard Replacement ~ D10103 |
- Design:
- Civil IFC Package complete.
- IFC secondary design package complete.
- Procurement:
- RMU package – in progress of shipment; ABB informed that there is a delay of two weeks. Melbourne Water has been informed about this and an early warning letter sent to Melbourne Water – delivery date 27 June.
- PLC package – in progress.
- HV Cables – delivered to site.
- FO Cables – delivered to site.
- Main Work Package
- Stage 1 Completion achieved on 11 March. Currently working on defects and hand over document.
ETP HV-62A Switchboard & VH-LV Renewals ~ Y10307 (Q05103) |
- Design:
- 62M in progress
- Procurement:
- 62M and 54M CEs procurement in progress
- Construction:
- Completed generators 3,5 and 7 cutover outage.
- Completed 6.6kV cable terminations for generator 3,5 and 7.
- Completed removal of redundant control cable associated with generator 3,5 and 7.
- Started excavation works of 54M kiosk transformer.
- Completed concrete pour for PFC foundations.
- OPS generator has been ordered.
- Unit sub 62M Melbourne Water design completed, procurement pending.
- Civil design for OPS generator completed, Astern quote received, and Melbourne Water approved in principle.
ETP Recuperative Thickener ~ Q05772 |
- Commissioning in progress.
- Asphalt works completed
- PLC52/53 code merge completed successfully on 25 May
ETP Waste Activated Sludge ~ Q05102 |
- ADXx electrical – continue terminating in 26MF switchboard. Installation of cables to field equipment.
- AMS – continue fitout of DAF Tanks 8,11 and 12. Continue installation of gallery pipework, saturator system for DAF Tanks 8, 11and 12.
- Completed civil/structural modifications in DAF tanks.
WTP Electrical Reliability Additional Works ~ F10133 |
- Design:
- IFC – design completed.
- CE – The revised protection study completed. Currently being reviewed by Melbourne Water
- Construction
- Schneider LLI works scheduled for Jan 2022 finished. The last set of LLIs initially scheduled for April postponed until protection study is completed.
- ABB LLI works completed. 25W Blower Building SCADA works are in progress
- Other
- An early warning letter has been submitted regarding the protection study. The planned activities can’t be completed until the protection study is approved
WTP 25W Lagoon Pond 1 HV and LV Renewals ~ F10461 |
- Design:
- Civil – IFC drawings completed
- MLC – Revised CFD report submitted for review
- Control Philosophy – Submitted for review
- Procurement:
- RMU – Ordered, delivery expected mid-October
- RMU Control Panel – Executing contract with Electro80
- HV Kiosks – Executing contract with Trivantage
- FO Cable – Delivered to Downer Dandenong Depot
- HV Cable – Ordered, delivery expected mid-July
- LV Cables – LV Cable Schedule being updated
- Construction:
- Civil works progressing (construction zones 1 & 2)
Gardiners Creek Sewer Rehabilitation ~ Y10248 |
- Lining works commenced.
- All lining materials ordered but the Covid impacts in China are delaying the CIPP materials delivery.
- Penstock removal commenced and 50% complete.
- CE1 submitted and approved.
- Traversing sewer and bypass system has commenced.
Maribyrnong Main Sewer Augmentation ~ P31258 |
- JV Partner still working through methodology for shaft and tunnelling works regarding subby/self perform engagement and to advice SFP on IR methodology. Advised it will be by the end of the week.
- Site preparations to begin excavation of launch shaft.
- Preparation of construction work pack documentation for Maribyrnong River access tracks.
- Commenced Hamstead Rd & Willamson Road crossovers.
- Continued site preparation for site concrete access road. Planning to finalise concrete road pour next week.
Interlocking Safety Upgrades for HV Water Sites ~ Y10260 |
- SE completed site visit to Cardinia to confirm key exchange boxes arrangement.
- Upcoming Activities:
- Completion of Project Management Documents.
- Execution of contract with SE for the installation works.
- Schneider Electric has confirmed the interlock kits have arrived.
- Preparation of outage permits for Silvan, Thomson, Cardinia and Preston.
- Prepare site works from 8 July.
Hoppers Crossing Pump Station 66kV ~ F10428 |
- APN received 13 May.
- PSD designer engaged.
- Handover and kick off completed.
- Kick off with designers completed.
- Meeting with AGGREKO regarding the variation (Power reliability) completed.
- Site investigation scope completed.
- DGM set up completed.
- Site investigation scope sent to market for pricing.
- Scope clarification meeting for Power Reliability variation was held with Melbourne Water.
- Development of management plans began.