Bid Status
Project | Job | Value | Status |
---|---|---|---|
ETP Areas 15-26 Upgrades | F10730 | $22M | Working |
North Yarra Main Relining Upper Section | Y10234 | $13M | Submitted |
WTP 55E Pond 1 MLC Renewal | F10427 | $15.7M | Submitted |
Project Delivery Update
M76 Water Main Renewal ~ Q02707 |
- APN issued.
- Kick off meeting completed.
- Management plans being issued.
- Negotiating with council and MWC to get traffic plans agreed so that service locating and proving completed.
- Negotiation with Monash Council on costs for the restoration of the football/cricket ground once works completed.
Essex Main Drain Renewal ~ Y10314 |
- Initial site investigations of stormwater channel completed.
- Design commenced.
- Resourcing – recruiting 1 x SPE for the project.
Maribyrnong Main Sewer Augmentation ~ P31258 |
- Launch Shaft depth: 35.6m.
- Currently progressing with shaft excavation in shorter lifts (500mm).
- Managing the water inflow away from the excavated face by extending the excavation below the base of the lift and digging drainage channels to a central sump. On recent lifts we have had to limit excavation to half the shaft (180°). This technique is allowing the shaft depth to progress in 500mm shotcrete lifts, with a shotcrete lift completion on a 4-5 day cycle.
- Note: Forecast completion of Shaft Excavation is 4th Aug 2023 (not including base).
- Riverside:
- Construction of haul road access to bridge abutment continuing.
- Shared user path sub-base preparation ongoing.
- Medway slope stability solution via 1:2 batter cut in work. Excavation and disposal of uncontrolled fill required.
- Receival shaft excavation progressing depth: 13.2m. (final depth is 14.8m).
- Bridge package awarded and shop drawings and heavy haulage transport investigations underway.
Yan Yean WTP Upgrade~ Q04385 |
- Cross contamination prevention works completed.
- Energization of MSB achieved 14 June.
- Continue pre-commissioning (wet) for equipment.
Yan Yean Pump Station ~ Q05322 |
- Finalizing IFC electrical, instrumentation and controls design.
- HV switchboard and valves arrived.
- Structural concrete at switch room, pump hall and valve chamber.
- Commencement of underground pipework at valve chamber.
- M190 tie-in planning in progress.
Yan Yean Bald Hill Pipeline ~ Q05333 |
- Site offices have been landed, with plumbing and breezeways being installed.
- Fencing of the pipeline corridor continuing.
- AMES mobilising to site and constructing compound.
- Negotiation of CE22 escalation ongoing need to get a response from Melbourne Water.
Hoppers Crossing Pump Station 66kV ~ F10428 |
- Final CHAZOP was completed on 15 June.
- Powercor has indicated it will upgrade its disconnector to a new RDB with Earth Switch in order to meet the Melbourne Water connection functional requirements. Awaiting Powercor to develop the scope involved with this upgrade.
- Proposal challenge session for Q03109 Power Reliability was held on 14/06 with Melbourne Water. MW has sent a memo to begin early works while their business case is being approved.
- Early procurement of Siemens CB has been approved for the pending Power Reliability variation works. Purchase Order is currently being raised.
- Fire System scope is currently under review by SFP.
WTP 25W Lagoon Pond 1 HV and LV Renewals ~ F10461 |
- Design
- LV and HV Control Narrative – Melbourne Water comments received. The documents will be finalised after all SAT/FAT have been completed.
- LV Protection and Arc Flash Report – Updated document issued for Melbourne Water review.
- HV Protection Report – Melbourne Water comments received. The documents will be finalised after all SAT/FAT have been completed.
- HV Arc Flash Report – Arc fault containment within LV switchboard being clarified with Melbourne Water. Waiting confirmation from Melbourne Water on the proposed solution to reduce arc flash rating.
- RMU Control Panel – Melbourne Water comments received.
- HV MOSAIC List – Issued for Melbourne Water review and implementation.
- HV Kiosks – IFC Drawings – Issued for Melbourne Water review.
- Procurement
- MLCs – All MLCs have been delivered.
- RMU – Delivered to Dandenong Depot.[LT1]
- HV Kiosks – Eaton has advised Trivantage the RMUs will be delayed by another 12 weeks.
- All HV, LV and FO cables have been delivered.
- Construction
- Civil
- Pre-cutover excavation works at 48ZFA MLC.
- Electrical
- Pre-commissioning works in MLCs around Pond 1.
- Terminate aerator cables at 48ZEA MLC.
- Punchlist items in MLCs around Pond 1.
- Testing and Commissioning
- Commission aerators at 48ZEA MLC.
- Civil
ETP HV-62A Switchboard & VH-LV Renewals ~ Y10307 (Q05103) |
- Continued redundant cable removal.
- Continued installation of 62ME3/4 cables and cutovers.
- Continued decommissioning of 62H
- Continued installation on 54HM2 Transformer works
- Completed removal of scaffolding installed for cable removal.
ETP Waste Activated Sludge ~ Q05102 |
- Investigation works ongoing for TWAS Pumps 8, 11 and 12 reduced performance.
- Global PLC cutover completed, testing ongoing.
- Commencement of Phase 2 PoPT to commence July 23.
ETP Recuperative Thickener ~ Q05772 |
- Works ongoing to complete PoPT.
Gardiners Creek Sewer Rehabilitation ~ Y10248 |
- Stage 1 issued.
- Stage 2 issued.
Holden Reservoir M486 Inlet Pipeline SP1 & SP2~ Q03295 |
- Stage 1 certificate received 8 April, 2022.
- Awaiting Melbourne Water to provide data for Stage 2 and 3.