Bid Status
Project | Job | Value | Status |
---|---|---|---|
ETP Areas 15-26 Upgrades | F10730 | $25.7M | Submitted |
WTP 55E Pond 1 MLC Renewal | F10427 | $15.7M | Submitted |
WTP HV Power & Energy Resilience ECI | Q03817 | $472K | Submitted |
Refurb of Werribee Hanger 1 | Y05707 | $23M | Working |
Port Melbourne Pump Station Renewal | Y10305 | $10M | Working |
Project Delivery Update
North Yarra Main Relining Upper Section ~ Y10234 |
- Site office has been acquired in Heidelberg.
- Cleaning program has commenced.
- Flow management plans being developed.
Tarago Fluoride Plant Upgrade ECI ~ Y10209 |
- Site visit and Melbourne Water kickoff meeting completed 2 September
M76 Water Main Renewal ~ Q02707 |
- Site office up and running.
- Pipe deliveries for oval works underway.
- Pipe crews onsite to start install.
Essex Main Drain Renewal ~ Y10314 |
- 80% design nearing completion.
- Constructability review booked in.
Maribyrnong Main Sewer Augmentation ~ P31258 |
- Launch Shaft depth: 39.5m.
- TBM preparation for Launch. Launch scheduled week commencing the 9 October.
- Riverside:
- Direction Notice #1 – Site has been demobilised
- Direction Notice #2: Siphon options assessment progressing – Two options are under review (1) Tunnel (TBM) from MH02 to MRM, and (2) Tunnel (TBM) from MH03 to MRM. O/L: late Nov 2023 for option recommendation. Geotech investigations to be undertaken in parallel.
Yan Yean WTP Upgrade~ Q04385 |
- Process commissioning continues.
- Chemical deliveries received on site (4 out of 6).
- Cleaning performed on GAS nozzles.
- Existing washwater transfer pumps being rectified for installation early October.
- Documentation submitted to DoH and scheduled for site verification in early October.
Yan Yean Pump Station ~ Q05322 |
- Structural steelwork installation completed.
- Underground pipework installation in progress.
- Installation of precast panels completed.
- Commenced FRP for RMU infrastructure.
- Surge vessels installation completed.
Yan Yean Bald Hill Pipeline ~ Q05333 |
- Pipe install commenced on Paddock section.
- Pipe install underway on Grants Rd.
- Tunnelling package of works agreed with Rob Carr.
- 650m of 9143m installed.
Hoppers Crossing Pump Station 66kV ~ F10428 |
- Geotech and surveying team has concluded site works. Results pending.
- Fire system valve isolation testing has been completed. Report from BlueFire has been received and is with the design team to asses impact on scope.
- Pricing for Q03109 to be finalised after fire system scope has been clarified.
WTP 25W Lagoon Pond 1 HV and LV Renewals ~ F10461 |
- HV cable terminations.
- Punchlist items in MLCs around Pond 1.
ETP HV-62A Switchboard & VH-LV Renewals ~ Y10307 (Q05103) |
- Completed installation of 62M switchboard including cable installation and load cutovers.
- Continued redundant cable removal.
- Completed installation and removal of temporary generator installed for 62M cutovers.
- Start and completed HV cutover of 62M from 62HA22.
ETP Waste Activated Sludge ~ Q05102 |
- Completed global code PLC defects 25 September.
- Larger shear pins installed on scrapers.
- TWAS pump investigation in progress.
- Closeout documentation in progress.
ETP Recuperative Thickener ~ Q05772 |
- 12 out of 14 performance test completed. H2S and noise testing commenced 26 September.
- Commissioning report and handover documentation compilation in progress.
Gardiners Creek Sewer Rehabilitation ~ Y10248 |
- Stage 1 issued.
- Stage 2 outstanding recent invoice issued for additional costs on as built design.
Holden Reservoir M486 Inlet Pipeline SP1 & SP2~ Q03295 |
- Stage 1 certificate received 8 April, 2022.
- Awaiting Melbourne Water to provide data for Stage 2 and 3.