Bid Status

ProjectJobValueStatus
ETP Areas 15-26 UpgradesF10730$25.7MSubmitted
WTP 55E Pond 1 MLC RenewalF10427$15.7MSubmitted
WTP HV Power & Energy Resilience ECIQ03817$472KSubmitted
Refurb of Werribee Hanger 1Y05707$23MWorking
Port Melbourne Pump Station RenewalY10305$10MWorking


Project Delivery Update

North Yarra Main Relining Upper Section ~ Y10234
  • Site office has been acquired in Heidelberg.
  • Cleaning program has commenced.
  • Flow management plans being developed.

Tarago Fluoride Plant Upgrade ECI ~ Y10209
  • Site visit and Melbourne Water kickoff meeting completed 2 September
M76 Water Main Renewal ~ Q02707
  • Site office up and running.
  • Pipe deliveries for oval works underway.
  • Pipe crews onsite to start install.

Essex Main Drain Renewal ~ Y10314
  • 80% design nearing completion.
  • Constructability review booked in.

Maribyrnong Main Sewer Augmentation ~ P31258
  • Launch Shaft depth: 39.5m.
    • TBM preparation for Launch. Launch scheduled week commencing the 9 October.
  • Riverside:
    • Direction Notice #1 – Site has been demobilised
    • Direction Notice #2: Siphon options assessment progressing – Two options are under review (1) Tunnel (TBM) from MH02 to MRM, and (2) Tunnel (TBM) from MH03 to MRM. O/L: late Nov 2023 for option recommendation. Geotech investigations to be undertaken in parallel.
Yan Yean WTP Upgrade~ Q04385
  • Process commissioning continues.
  • Chemical deliveries received on site (4 out of 6).
  • Cleaning performed on GAS nozzles.
  • Existing washwater transfer pumps being rectified for installation early October.
  • Documentation submitted to DoH and scheduled for site verification in early October.
Yan Yean Pump Station ~ Q05322
  • Structural steelwork installation completed.
  • Underground pipework installation in progress.
  • Installation of precast panels completed.
  • Commenced FRP for RMU infrastructure.
  • Surge vessels installation completed.
Yan Yean Bald Hill Pipeline ~ Q05333
  • Pipe install commenced on Paddock section.
  • Pipe install underway on Grants Rd.
  • Tunnelling package of works agreed with Rob Carr.
  • 650m of 9143m installed.
Hoppers Crossing Pump Station 66kV ~ F10428
  • Geotech and surveying team has concluded site works. Results pending.
  • Fire system valve isolation testing has been completed. Report from BlueFire has been received and is with the design team to asses impact on scope.
  • Pricing for Q03109 to be finalised after fire system scope has been clarified.
WTP 25W Lagoon Pond 1 HV and LV Renewals ~ F10461
  • HV cable terminations.
  • Punchlist items in MLCs around Pond 1.
ETP HV-62A Switchboard & VH-LV Renewals ~ Y10307 (Q05103)
  • Completed installation of 62M switchboard including cable installation and load cutovers.
  • Continued redundant cable removal.
  • Completed installation and removal of temporary generator installed for 62M cutovers.
  • Start and completed HV cutover of 62M from 62HA22.
ETP Waste Activated Sludge ~ Q05102
  • Completed global code PLC defects 25 September.
  • Larger shear pins installed on scrapers.
  • TWAS pump investigation in progress.
  • Closeout documentation in progress.
ETP Recuperative Thickener ~ Q05772
  • 12 out of 14 performance test completed. H2S and noise testing commenced 26 September.
  • Commissioning report and handover documentation compilation in progress.
Gardiners Creek Sewer Rehabilitation ~ Y10248
  • Stage 1 issued.
  • Stage 2 outstanding recent invoice issued for additional costs on as built design.
Holden Reservoir M486 Inlet Pipeline SP1 & SP2~ Q03295
  • Stage 1 certificate received 8 April, 2022.
  • Awaiting Melbourne Water to provide data for Stage 2 and 3.