Bid Status
Project | Job | Value | Status |
---|---|---|---|
Thomson Dam Capacitor Upgrade | Y10364 | $3.5M | Won |
Tarago Fluoride Plant Upgrade | Y10209 | $10M | Won |
WTS Emergency Management Plan | Q05622 | $250k | Won |
Upper Yarra Dam Ogee Weir Remediation | F10758 | $3.5M | Submitted |
Silvan High Security Fence | Y10337 | $301k | Submitted |
Refurb of Werribee Hangar 1 | Q05707 | $29.6M | Submitted |
Maribyrnong Siphon | P31258 | $69.9M | Submitted |
ETP Excess Solids Interim Risk Management (Centrifuge) | Y10286 | $11.6M | Working |
Winneke Filter Refurbishment | F10346 | $42M | Working |
WTP HV Power & Energy Resilience | Q03817 | $65M | Working |
Elsternwick Creek and Elwood MD Flood Mitigation Works | D10134 | $50M | Working |
Project Delivery Update
North Heatherton Wetland Renewal ~ F10448 |
- Temporary shared user path and haul roads completed
- Frog fencing completed
- Installation of site shed facility in progress
Tarago Fluoride Plant Upgrade ~ Y10209 |
- Detailed design in progress
M76 Water Main Renewal ~ Q02707 |
- All MWC and YVW pipework completed – Major Milestone
- 3 x pipelaying crews including nightshift works
- Reinstatement works for Monash Reserve car park commenced
- Backing filling of basin outlet completed
- Electrical and comms conduits installation
- Electrical cabinets delivered
- Commenced grouting work of redundant M76
Essex Main Drain Renewal ~ Y10314 |
- Erica Street Works:
- Completed DN 1200 RCP installation to replace existing drain.
- Completed tie-in transition pit.
- Completed benching min transition pits.
- Completed preparation for remaining asphalt.
Maribyrnong Main Sewer Augmentation ~ P31258 |
- Launch Shaft:
- Pipe Joint testing 90% complete
- Adit preparation works:
• Dewatering spear installation complete
• Stitch core of thrust wall in preparation for Adit shield underway
• Jacking shield fabrication complete and on site
• Thrust beam installation underway
- Riverside
- No change – further discussion with Melbourne Water regarding Change Event #24 required
Yan Yean WTP Upgrade ~ Q04385 |
- Awaiting Stage 1 completion
- Closing out Stage 2 items and project closeout
Yan Yean Pump Station ~ Q05322 |
- Proof of Performance completed 7 November
- Closeout of Stage 2 items in progress
Yan Yean Bald Hill Pipeline ~ Q05333 |
- Applied for stage 1 completion 27 November
- Completed LFI/EPR
Hoppers Crossing Pump Station 66kV ~ F10428 |
- CE03 F10428 Delay Costs and Scope Changes – submitted to Melbourne Water – urgent approval required
- CE04 Extended Generator Compound – submitted to Melbourne Water -urgent approval required
- Comments for the 80% civil design package for Q03109 Power Reliability has been received from Melbourne Water.
- 80% electrical primary design package for Q03109 Power Reliability has been issued to Melbourne Water for review on 18 November. Waiting on comments from Melbourne Water.
- RMU Control Box drawings for Q03109 Power reliability have been issued to Melbourne Water for review on 13 November. Waiting on comments from Melbourne Water.
- Fire remediation is underway. The team has excavated, identified and capped off known irrigation points. Hydrostatic pressure testing has been completed. There are no issues with the modification works that SFPJV have completed; however, the pressure test has revealed other existing issue which now need to be resolved:
- There is a leak in the “ATF” leg of the fire main. Leak has been repaired on 12 November.
- The “Chemical Dosing” leg of the fire main is currently mix-use (potable water and fire services). Old line has been disconnected from the fire mains and a new line has been connected to the water mains.
- Pressure testing performed on 02 December
WTP 55 Pond MLC Renewal ~ F10427 |
- WTP 25W
- Awaiting Stage 2 Certificate
- WTP 55E
- MLCs – contract with Trivantage executed. PO being raised.
- 24V DC Battery Charger Calculation – approved by Melbourne Water.
- HV Alignment Drawings 80% – approved by Melbourne Water.
- 100% Control Philosophy – approved by Melbourne Water.
- 30% Control Package – received comments from Melbourne Water.
WTP 66kV ~ F10461 |
- Tender Received from Melbourne Water. The submission date is 3 March 2025
- Project team is working on the tender. Kick off has been organised for this week
Thompson Hydro Capacitor Bank – Y10364 |
- PLC Procurement – Contract Executed
- Progressing with Electrical Design
ETP Waste Activated Sludge ~ Q05102 |
- Phase 2 PoPT in progress. To be completed in September.
- Investigations ongoing for TWAS pump priming issue.
- Closeout of defects in progress.
ETP Recuperative Thickener ~ Q05772 |
- Closing out Stage 2 items.
ETP Areas 15 to 26 ~ F10730 |
- PLC Procurement – Contract Executed
- Progressing with Electrical Design Location of PCS cabinets
- Profinet and Profibus solution sent to Melbourne Water, general solution has been accepted, currently working on package to submit
- Final solution has been approved, costs are being evaluated by design team.
- Costs to be provided from Stantec to the PM team
- Costs provided to the PM Team currently being reviewed
- 24VDC Specs comments received from Melbourne Water on 21 November
- 24VDC sizing reports sent to Melbourne Water on 28 October
LV override assessment report sent to Melbourne Water for review - Meeting between Melbourne Water and SFPJV to 27 November for review
- Area 15 Enclosure comments received from Melbourne Water on 21 November
- Electrical Secondary design 30%
- Comments received from Melbourne Water on 21 November
- Meeting with Melbourne Water to clarify details as requested, 27 November
- LV Switchboards IFT Packages comments received from Melbourne Water on 21 November
- Electrical design reports 30% comments received from Melbourne Water on 21 November
- CE01 pending with Melbourne Water
M76 Water Main Renewal ~ Q02707 |
- All MWC and YVW pipework completed – Major Milestone
- 3 x pipelaying crews including nightshift works
- Reinstatement works for Monash Reseve car park commenced
- Backing filling of basin outlet completed
- Electrical and comms conduits installation
- Electrical cabinets delivered
- Commenced grouting work of redundant M76
Essex Main Drain Renewal ~ Y10314 |
- Erica Street Works:
- Completed DN 1200 RCP installation to replace existing drain.
- Completed tie-in transition pit.
- Completed benching min transition pits.
- Completed preparation for remaining asphalt.
Maribyrnong Main Sewer Augmentation ~ P31258 |
- Launch Shaft:
- Pipe Joint testing 90% complete
- Adit preparation works:
• Dewatering spear installation complete
• Stich core of thrust wall in preparation for Adit shield underway
• Jacking shield fabrication complete and on site
• Thrust beam installation underway
- Riverside
- No change – further discussion with Melbourne Water regarding Change Event #24 required
Yan Yean WTP Upgrade ~ Q04385 |
- Awaiting Stage 1 completion
- Closing out Stage 2 items and project closeout
Yan Yean Pump Station ~ Q05322 |
- Proof of Performance completed 7 November
- Closeout of Stage 2 items in progress
Yan Yean Bald Hill Pipeline ~ Q05333 |
- Applied for stage 1 completion 27 November
- Completed LFI/EPR
Hoppers Crossing Pump Station 66kV ~ F10428 |
- CE03 F10428 Delay Costs and Scope Changes – submitted to Melbourne Water – urgent approval required
- CE04 Extended Generator Compound – submitted to Melbourne Water -urgent approval required
- Comments for the 80% civil design package for Q03109 Power Reliability has been received from Melbourne Water.
- 80% electrical primary design package for Q03109 Power Reliability has been issued to Melbourne Water for review on 18/11. Waiting on comments from Melbourne Water.
- RMU Control Box drawings for Q03109 Power reliability have been issued to Melbourne Water for review on 13/11. Waiting on comments from Melbourne Water.
- Fire remediation is underway. The team has excavated, identified and capped off known irrigation points. Hydrostatic pressure testing has been completed. There are no issues with the modification works that SFPJV have completed; however, the pressure test has revealed other existing issue which now need to be resolved:
- There is a leak in the “ATF” leg of the fire main. Leak has been repaired on 12 November.
- The “Chemical Dosing” leg of the fire main is currently mix-use (potable water and fire services). Old line has been disconnected from the fire mains and a new line has been connected to the water mains.
- Pressure testing performed on 02 December
WTP 55 Pond MLC Renewal ~ F10427 |
- WTP 25W
- Awaiting Stage 2 Certificate
- WTP 55E
- MLCs – contract with Trivantage executed. PO being raised.
- 24V DC Battery Charger Calculation – approved by Melbourne Water.
- HV Alignment Drawings 80% – approved by Melbourne Water.
- 100% Control Philosophy – approved by Melbourne Water.
- 30% Control Package – received comments from Melbourne Water.
WTP 66kV ~ F10461 |
- Tender Received from Melbourne Water. The submission date is3 March 2025
- Project team is working on the tender. Kick off has been organised for this week
Thompson Hydro Capacitor Bank – Y10364 |
- PLC Procurement – Contract Executed
- Progressing with Electrical Design
ETP Waste Activated Sludge ~ Q05102 |
- Phase 2 PoPT in progress. To be completed in September.
- Investigations ongoing for TWAS pump priming issue.
- Closeout of defects in progress.
ETP Recuperative Thickener ~ Q05772 |
- Closing out Stage 2 items.
ETP Areas 15 to 26 ~ F10730 |
- PLC Procurement – Contract Executed
- Progressing with Electrical Design Location of PCS cabinets have been agreed on
- Profinet and Profibus solution sent to Melbourne Water, general solution has been accepted, currently working on package to submit
- Final solution has been approved, costs are being evaluated by design team.
- Costs to be provided from Stantec to the PM team
- Costs provided to the PM Team currently being reviewed
- 24VDC Specs comments received from Melbourne Water on 21 November
- 24VDC sizing reports sent to Melbourne Water on 28 October
LV override assessment report sent to Melbourne Water for review - Meeting for report being held by Melbourne Water on 12 November
- Meeting between Melbourne Water and SFPJV to 27/11/24 for review
- Area 15 Enclosure comments received from Melbourne Water on 21 November
- Electrical Secondary design 30%
- Comments received from Melbourne Water on 21 November
- Meeting with Melbourne Water to clarify details as requested, 27 November
- LV Switchboards IFT Packages comments received from Melbourne Water on 21 November
- Electrical design reports 30% comments received from Melbourne Water on 21 November
- CE01 pending with Melbourne Water