Bid Status
Project | Job | Value | Status |
---|---|---|---|
Silvan High Security Fence | Y10337 | $620k | Won |
Refurb of Werribee Hangar 1 | Q05707 | $29.6M | Submitted |
Maribyrnong Siphon | P31258 | $69.9M | Submitted |
ETP Excess Solids Interim Risk Management (Centrifuge) | Y10286 | $11.6M | Submitted |
Winneke Filter Refurbishment | F10346 | $42M | Working |
WTP HV Power & Energy Resilience | Q03817 | $65M | Submitted |
Elsternwick Creek and Elwood MD Flood Mitigation Works | D10134 | $87M | Submitted |
Lang Lang River Head Fishlock | Y10365 | $4.8M | Working |
East Minor Capital works | $4.3M | Working |
Project Delivery Update

North Heatherton Wetland Renewal ~ F10448 |
- Acid Sulphate Treatment of sediment complete
- Green Waste disposal offsite
- Condition clay and sediment for placement
- Pit 2 & Pit 5 works
- Pit 4 and drainage works

Tarago Fluoride Plant Upgrade ~ Y10209 |
- Detailed design in progress
- Site Shed connections complete
- Soil Testing completed for Waste Classification
- Civil contract awarded, mobilisation first week of March
- RRF’s out for Mechanical and Electrical Equipment
- UV procurement schedule revised and back on track

M76 Water Main Renewal ~ Q02707 |
- Asphalting completed in High Street Rd
- Stage 1 Completion – 13th December requested.
- Undertaking defect list items
- Change Event/Separable Portion submitted for YVW Pump Station connection
- Demobilisation activities

Essex Main Drain Renewal ~ Y10314 |
- Stage 1 Completion – 13th December requested.

Maribyrnong Main Sewer Augmentation ~ P31258 |
Tunnelling (incl. Adit):
- Hand excavation reached the NWS on the 13th Feb 2025.
- The concrete collar at NWS interface has been formed and poured. OD900mm core for live break-in to NWS has commenced.
- DN750 pipe installation to follow.
- GRP Pipe repairs: Continuing to pursue subcontractors to complete this work.

Yan Yean WTP Upgrade ~ Q04385 |
- Awaiting Stage 1 completion
- Closing out Stage 2 items and project closeout
Yan Yean Pump Station ~ Q05322 |
- Closeout of Stage 2 items in progress

Yan Yean Bald Hill Pipeline ~ Q05333 |
- Stage 1 completion obtained for 27/11/24
- Stage 2 documents submitted 24/01/25
- Fabrication for CE42 manifold has commenced
- Awaiting finalised design for Manifold

Hoppers Crossing Pump Station 66kV ~ F10428 |
- LV Interface Panel is under manufacturing
- RMU Control Box is under manufacturing
- Electrical IFCs are currently under internal review
- Site sheds have been landed. Electrical and plumbing services outstanding.
- Tree removal has been completed
- Mobilisation of civil works underway
Change Events
- CE03 F10428 Delay Costs & Scope Changes – Pricing has been submitted to MW on 25/09. Waiting approval.
- CE04 Q03109 Extended Generator Compound – Pricing has been submitted to MW on 25/09. MW have instructed SFPJV to proceed with CE04 while they are reviewing the costs. Endorsement to continue has been received.

WTP 55 Pond MLC Renewal ~ F10427 |
WTP 25W
- Still issues with Asset management MW. Meetings organised with MW to address the issues
- Still haven’t received the final comments on SFPJVs Stage 2 Hand over documents.
WTP 55E
- Safety in Design CHAIR – Held on 27 Feb.
- CFD Report – Under MW/SFP review.
- Site mobilisation – Progressing.
- MLC 80% design – Progressing.
- HV cable – Delivery end of May.
- Fibre optic cable – PO raised. Delivery date TBA.
Early Warning – MLC Review Process Delay sent on 18/6.
WTP 66kV ~ F10461 |
Tender Submitted to MW on 3rd March

Thompson Hydro Capacitor Bank – Y10364 |
- IFC Control Philosophy – In Progress. Meeting held with MW last week again to finalise this
- Submitted design deliverables are being reviewed by MW
- Protection Settings report to be submitted to MW today
- LV Cables ordered
- MW Directed SFPJV to postpone the commissioning by 4 weeks. This will delay the PC date. PM is assessing the impact

ETP Waste Activated Sludge ~ Q05102 |
- MW comments on Phase 2 PoPT report in progress
- TWAS pump testing including additional valve installation
- Closeout of defects in progress

ETP Recuperative Thickener ~ Q05772 |
- Closing out Stage 2 items
- Review of MW comments on PoPT report and planning for additional testing in Mar 2025

ETP Areas 15 to 26 ~ F10730 |
- PCS CC# 3 – PCS CC#5 positioning is being evaluated.
- Costs provided to the MW, currently being reviewed, discussions to be had
- 24VDC sizing reports updated, currently being sent to suppliers
- Quotes have been received by some suppliers
- LV override assessment report sent to MW for review
- Meeting held with MW, currently being reviewed by MW
- Will be addressed after MW has a review meeting
- Area 15 Enclosure design team progressing with 80%
- Specs issued to suppliers for quotes
- 80% issues to SFPJV
- Electrical Primary design 80%
- Issued to MW
- Electrical Secondary design 80% sent for area 26
- No existing drawings have been sent, only new drawings, meeting held to address missing drawings and critical drawings.
- LV Switchboards IFT Packages design team progressing with 80%
- Specs issued to suppliers for quotes
- Electrical design reports, design team progressing with 80%
- Civil Design 80% Area 26 sent to MW
- Structural Design 80% Area 26 sent to MW
- Structural Design 80% Area 21 sent to MW
- Architectural design 60% Area 26, sent to MW
- Mechanical Design 80%, Area 26 sent to MW
- Structural design 80%, Area 15 sent to MW
- Civil design 80%, area 15 sent to MW

Mordialloc Main Sewer Rehabilitation – Y10334 |
- CCTV, cleaning and ovality scanning completed for all sections
- MRD2 exposed and awaiting design memo for rectification works
- Liner design change memo submitted to MWC for review and approval
- General manhole modifications scheduled to be commenced in Mid-March