Bid Status

ProjectJobValueStatus
Silvan High Security FenceY10337$620kWon
Refurb of Werribee Hangar 1Q05707$29.6MSubmitted
Maribyrnong SiphonP31258$69.9MSubmitted
ETP Excess Solids Interim Risk Management (Centrifuge)Y10286$11.6MSubmitted
Winneke Filter RefurbishmentF10346$42MWorking
WTP HV Power & Energy Resilience Q03817$65MSubmitted
Elsternwick Creek and Elwood MD Flood Mitigation WorksD10134$87MSubmitted
Lang Lang River Head FishlockY10365$4.8MWorking
East Minor Capital works$4.3MWorking

Project Delivery Update

North Heatherton Wetland Renewal ~ F10448
  • Acid Sulphate Treatment of sediment complete
  • Green Waste disposal offsite
  • Condition clay and sediment for placement
  • Pit 2 & Pit 5 works
  • Pit 4 and drainage works

Tarago Fluoride Plant Upgrade ~ Y10209
  • Detailed design in progress
  • Site Shed connections complete
  • Soil Testing completed for Waste Classification
  • Civil contract awarded, mobilisation first week of March
  • RRF’s out for Mechanical and Electrical Equipment
  • UV procurement schedule revised and back on track

M76 Water Main Renewal ~ Q02707
  • Asphalting completed in High Street Rd
  • Stage 1 Completion – 13th December requested.
  • Undertaking defect list items
  • Change Event/Separable Portion submitted for YVW Pump Station connection
  • Demobilisation activities

Essex Main Drain Renewal ~ Y10314
  • Stage 1 Completion – 13th December requested.

    Maribyrnong Main Sewer Augmentation ~ P31258

      Tunnelling (incl. Adit):

      • Hand excavation reached the NWS on the 13th Feb 2025.
      • The concrete collar at NWS interface has been formed and poured. OD900mm core for live break-in to NWS has commenced.
      • DN750 pipe installation to follow.
      • GRP Pipe repairs:  Continuing to pursue subcontractors to complete this work.
      Yan Yean WTP Upgrade ~ Q04385
      • Awaiting Stage 1 completion
      • Closing out Stage 2 items and project closeout
      Yan Yean Pump Station ~ Q05322
      • Closeout of Stage 2 items in progress
      Yan Yean Bald Hill Pipeline ~ Q05333
      • Stage 1 completion obtained for 27/11/24
      • Stage 2 documents submitted 24/01/25
      • Fabrication for CE42 manifold has commenced
      • Awaiting finalised design for Manifold
      Hoppers Crossing Pump Station 66kV ~ F10428
      • LV Interface Panel is under manufacturing
      • RMU Control Box is under manufacturing
      • Electrical IFCs are currently under internal review
      • Site sheds have been landed. Electrical and plumbing services outstanding.
      • Tree removal has been completed
      • Mobilisation of civil works underway

      Change Events

      • CE03 F10428 Delay Costs & Scope Changes – Pricing has been submitted to MW on 25/09. Waiting approval.
      • CE04 Q03109 Extended Generator Compound – Pricing has been submitted to MW on 25/09. MW have instructed SFPJV to proceed with CE04 while they are reviewing the costs. Endorsement to continue has been received.
       WTP 55 Pond MLC Renewal ~ F10427

      WTP 25W

      • Still issues with Asset management MW. Meetings organised with MW to address the issues
      • Still haven’t received the final comments on SFPJVs Stage 2 Hand over documents. 

      WTP 55E

      • Safety in Design CHAIR – Held on 27 Feb.
      • CFD Report – Under MW/SFP review.
      • Site mobilisation – Progressing.
      • MLC 80% design – Progressing.
      • HV cable – Delivery end of May. 
      • Fibre optic cable – PO raised. Delivery date TBA.

      Early Warning – MLC Review Process Delay sent on 18/6.

       WTP 66kV ~ F10461

      Tender Submitted to MW on 3rd March

        Thompson Hydro Capacitor Bank – Y10364
        • IFC Control Philosophy – In Progress. Meeting held with MW last week again to finalise this
        • Submitted design deliverables are being reviewed by MW
        • Protection Settings report to be submitted to MW today
        • LV Cables ordered
        • MW Directed SFPJV to postpone the commissioning by 4 weeks. This will delay the PC date. PM is assessing the impact
        ETP Waste Activated Sludge ~ Q05102
        • MW comments on Phase 2 PoPT report in progress
        • TWAS pump testing including additional valve installation
        • Closeout of defects in progress
        ETP Recuperative Thickener ~ Q05772
        • Closing out Stage 2 items
        • Review of MW comments on PoPT report and planning for additional testing in Mar 2025
        ETP Areas 15 to 26 ~ F10730
        • PCS CC# 3 – PCS CC#5 positioning is being evaluated.
        • Costs provided to the MW, currently being reviewed, discussions to be had
        •  24VDC sizing reports updated, currently being sent to suppliers
        • Quotes have been received by some suppliers
        • LV override assessment report sent to MW for review
        • Meeting held with MW, currently being reviewed by MW
        • Will be addressed after MW has a review meeting
        • Area 15 Enclosure design team progressing with 80%
        • Specs issued to suppliers for quotes
        • 80% issues to SFPJV
        • Electrical Primary design 80%
        • Issued to MW
        • Electrical Secondary design 80% sent for area 26
        • No existing drawings have been sent, only new drawings, meeting held to address missing drawings and critical drawings.
        • LV Switchboards IFT Packages design team progressing with 80%
        • Specs issued to suppliers for quotes
        • Electrical design reports, design team progressing with 80%
        • Civil Design 80% Area 26 sent to MW
        • Structural Design 80% Area 26 sent to MW
        • Structural Design 80% Area 21 sent to MW
        • Architectural design 60% Area 26, sent to MW
        • Mechanical Design 80%, Area 26 sent to MW
        • Structural design 80%, Area 15 sent to MW
        • Civil design 80%, area 15 sent to MW
        Mordialloc Main Sewer Rehabilitation – Y10334
        • CCTV, cleaning and ovality scanning completed for all sections
        • MRD2 exposed and awaiting design memo for rectification works
        • Liner design change memo submitted to MWC for review and approval
        • General manhole modifications scheduled to be commenced in Mid-March