Bid Status
Project | Job | Value | Status |
---|---|---|---|
Mordialloc Main Sewer Rehab | Y10341 | $12.4M | Won |
Refurb of Werribee Hanger 1 | Y05707 | $23M | Submitted |
ETP Digester Upgrades | Y10286 | $70M | Lost |
Thomson Dam Capacitor Upgrade | Y10364 | $3.5M | Won |
Tarago Fluoride Plant Upgrade | Y10209 | $10M | Submitted |
WTS Emergency Management Plan | Q05622 | $250k | Submitted |
North Heatherton Wetland Renewal | F10465 | $10M | Won |
Waverley Rd Retarding Basin Spillway | F10476 | $5M | Submitted |
WTP HV Power & Energy Resilience FD | Q03817 | $237k | Submitted |
Project Delivery Update
North Yarra Main Relining Upper Section ~ Y10234 |
- Stage 1 Completion certificate received 8 August
- Lessons learnt workshop with Melbourne Water completed 20 August
- 7 of 14 junction seal completed ( 3No lines remain) programmed for first week of October
M76 Water Main Renewal ~ Q02707 |
- Carpark works completed
- Nightworks on High St – Fleet St connections works completed including installation of air valve at High St Road.
- New M76 Pressure Testing & Chlorination passed pressure and leak test.
- Southern Basin Slip Lining Works:
- Additional NDD investigations to find unknown asset(s) on upcoming slip-lining works.
- Removal of asbestos and abundant pipework from southern outlet completed
Valve hut demolition and SCADA power run completed
- Fleet St:
- Remaining pipework completed including installation of DN450 Magflow flowmeter and gate valve (including bypass).
- Cathodic protection test point installation on DN450 Magflow flowmeter.
Essex Main Drain Renewal ~ Y10314 |
- Erica Street Works:
- Concrete slab and walls finished for pit on Williams Rd end.
- Shotcreted chamber under Williams Rd to connect to pit.
- Start of DN 1200 RCP installation to replace existing drain.
Maribyrnong Main Sewer Augmentation ~ P31258 |
- Launch Shaft:
- Tunnel stripping complete, Grouting and Joint testing to follow in parallel with Adit preparation works.
- Demobilisation of Tunnelling equipment ongoing
- Geotech core samples complete
- Adit
- Jacking shield fabrication underway.
- Riverside
- Nothing to report
Yan Yean WTP Upgrade ~ Q04385 |
- PoPT completed 21 August
- Closing out Stage 1 items and project closeout
Yan Yean Pump Station ~ Q05322 |
- Closeout of Stage 2 items in progress.
- Surge vessel pressure test completed.
- Sequence testing completed on cooling skids and system (excluding HV pumps).
Yan Yean Bald Hill Pipeline ~ Q05333 |
- Delcon pipeline up Bald Hill has 100m to go
- Merri Creek tunnel completed
- Rail tunnel mobilised and planning to commence
- GLE crews commenced leading pipework either side of tunnels
- LFI EPR earth stakes installed
- Grants Road asphalt placement completed
Hoppers Crossing Pump Station 66kV ~ F10428 |
- Q03109 Power Reliability 80% Design Package in development.
- Follow-up design meeting with Aggreko and Melbourne Water was held on 21 August. RFI raised with Melbourne Water to confirm if cable culverts can be omitted from current design.
- Currently in negotiations with Rangedale to finalise scope and pricing for the fire remediation works. Contract currently under negotiation.
- Planning for early works mobilisation.
WTP 55 East HV/LV (CE to 25W) ~ F10427 |
- Fibre Routing drawings issued for review on 18 June. Route discussed during Melbourne Water/SFP site walkthrough on 21 August. Awaiting approval from Melbourne Water.
- Change Event for new site facility and laydown area submitted on 7 June. Awaiting approval from Melbourne Water.
- Closing out final technical items with Melbourne Water for the MLC requirements.
- Reviewing updated offer from Trivantage for the MLC package.
- Submitted Control Philosophy to Melbourne Water for review on 5 August.
- Submitted HV Cable and Conductor Sizing Report to Melbourne Water for review on 8 August.
- Submitted EMP and CEMP Poster to Melbourne Water for review on 14 August.
WTP 66kV ~ F10461 |
- Final SOW submitted to Melbourne Water
- Melbourne Water intends to first issue the project for Design only.
- PN for the Functional design received – Currently SFPJV is working on the tender submission. Meetings with Design and Tender Team are ongoing. The tender submission is on track
Thompson Hydro Capacitor Bank – Y10364 |
- APN received.
ETP Waste Activated Sludge ~ Q05102 |
- Phase 2 PoPT in progress. To be completed in September.
- Investigations ongoing for TWAS pump priming issue.
- Closeout of defects in progress.
ETP Recuperative Thickener ~ Q05772 |
- Closing out Stage 2 items.
ETP Areas 15 to 26 ~ F10730 |
- AM STA 3700 Specs are to be used, new quotes will be approved before procurement of Kiosks:
- ABB selected as preferred supplier due to specs and pricing.
- Currently doing technical and commercial negotiations
- HV Cables IFTs have been received.
- All technical reviews completed, Olex selected as preferred supplier.
- Contract establishment process in progress
- Contract has been put on hold for a moment as details about the cables needs to be clarified regarding termite protection and length
- All 30% design drawing deliverables (Civil, Electrical and Structural) are sent to Melbourne Water, Melbourne Water has sent back comments, to be closed out next week.
- 30% electrical reports sent to Melbourne Water . Comments expected next week.
- PCS CC# 3 – PCS CC#5 positioning is being evaluated.
- location of PCS cabinets have been agreed on.
- Profinet and Profibus solution sent to MW, currently under review.