Bid Status

ProjectJobValueStatus
Mordialloc Main Sewer RehabY10341$12.4MWon
Refurb of Werribee Hanger 1Y05707$23MSubmitted
ETP Digester UpgradesY10286$70MLost
Thomson Dam Capacitor UpgradeY10364$3.5MWon
Tarago Fluoride Plant UpgradeY10209$10MSubmitted
WTS Emergency Management PlanQ05622$250kSubmitted
North Heatherton Wetland RenewalF10465$10MWon
Waverley Rd Retarding Basin SpillwayF10476$5MSubmitted
WTP HV Power & Energy Resilience FDQ03817$237kSubmitted

Project Delivery Update

North Yarra Main Relining Upper Section ~ Y10234
  • Stage 1 Completion certificate received 8 August
  • Lessons learnt workshop with Melbourne Water completed 20 August
  • 7 of 14 junction seal completed ( 3No lines remain) programmed for first week of October

M76 Water Main Renewal ~ Q02707
  • Carpark works completed
  • Nightworks on High St – Fleet St connections works completed including installation of air valve at High St Road.
  • New M76 Pressure Testing & Chlorination passed pressure and leak test.
  • Southern Basin Slip Lining Works:
    • Additional NDD investigations to find unknown asset(s) on upcoming slip-lining works.
    • Removal of asbestos and abundant pipework from southern outlet completed
      Valve hut demolition and SCADA power run completed
  • Fleet St:
    • Remaining pipework completed including installation of DN450 Magflow flowmeter and gate valve (including bypass).
    • Cathodic protection test point installation on DN450 Magflow flowmeter.

Essex Main Drain Renewal ~ Y10314
  • Erica Street Works:
    • Concrete slab and walls finished for pit on Williams Rd end.
    • Shotcreted chamber under Williams Rd to connect to pit.
    • Start of DN 1200 RCP installation to replace existing drain.

Maribyrnong Main Sewer Augmentation ~ P31258
  • Launch Shaft:
    • Tunnel stripping complete, Grouting and Joint testing to follow in parallel with Adit preparation works.
    • Demobilisation of Tunnelling equipment ongoing
    • Geotech core samples complete
  • Adit
    • Jacking shield fabrication underway.
  • Riverside
    • Nothing to report
Yan Yean WTP Upgrade ~ Q04385
  • PoPT completed 21 August
  • Closing out Stage 1 items and project closeout
Yan Yean Pump Station ~ Q05322
  • Closeout of Stage 2 items in progress.
  • Surge vessel pressure test completed.
  • Sequence testing completed on cooling skids and system (excluding HV pumps).
Yan Yean Bald Hill Pipeline ~ Q05333
  • Delcon pipeline up Bald Hill has 100m to go
  • Merri Creek tunnel completed
  • Rail tunnel mobilised and planning to commence
  • GLE crews commenced leading pipework either side of tunnels
  • LFI EPR earth stakes installed
  • Grants Road asphalt placement completed
Hoppers Crossing Pump Station 66kV ~ F10428
  • Q03109 Power Reliability 80% Design Package in development.
  • Follow-up design meeting with Aggreko and Melbourne Water was held on 21 August. RFI raised with Melbourne Water to confirm if cable culverts can be omitted from current design.
  • Currently in negotiations with Rangedale to finalise scope and pricing for the fire remediation works. Contract currently under negotiation.
  • Planning for early works mobilisation.
 WTP 55 East HV/LV (CE to 25W) ~ F10427
  • Fibre Routing drawings issued for review on 18 June. Route discussed during Melbourne Water/SFP site walkthrough on 21 August. Awaiting approval from Melbourne Water.
  • Change Event for new site facility and laydown area submitted on 7 June. Awaiting approval from Melbourne Water.
  • Closing out final technical items with Melbourne Water for the MLC requirements.
  • Reviewing updated offer from Trivantage for the MLC package.
  • Submitted Control Philosophy to Melbourne Water for review on 5 August.
  • Submitted HV Cable and Conductor Sizing Report to Melbourne Water for review on 8 August.
  • Submitted EMP and CEMP Poster to Melbourne Water for review on 14 August.
 WTP 66kV ~ F10461
  • Final SOW submitted to Melbourne Water
  • Melbourne Water intends to first issue the project for Design only.
  • PN for the Functional design received – Currently SFPJV is working on the tender submission. Meetings with Design and Tender Team are ongoing. The tender submission is on track
Thompson Hydro Capacitor Bank – Y10364
  • APN received.
ETP Waste Activated Sludge ~ Q05102
  • Phase 2 PoPT in progress. To be completed in September.
  • Investigations ongoing for TWAS pump priming issue.
  • Closeout of defects in progress.
ETP Recuperative Thickener ~ Q05772
  • Closing out Stage 2 items.
ETP Areas 15 to 26 ~ F10730
  • AM STA 3700 Specs are to be used, new quotes will be approved before procurement of Kiosks:
    • ABB selected as preferred supplier due to specs and pricing.
    • Currently doing technical and commercial negotiations
  • HV Cables IFTs have been received.
    • All technical reviews completed, Olex selected as preferred supplier.
    • Contract establishment process in progress
    • Contract has been put on hold for a moment as details about the cables needs to be clarified regarding termite protection and length
  • All 30% design drawing deliverables (Civil, Electrical and Structural) are sent to Melbourne Water, Melbourne Water has sent back comments, to be closed out next week.
  • 30% electrical reports sent to Melbourne Water . Comments expected next week.
  • PCS CC# 3 – PCS CC#5 positioning is being evaluated.
    • location of PCS cabinets have been agreed on.
    • Profinet and Profibus solution sent to MW, currently under review.